Organisation

Work/Task Breakdown

 

 

Task 

Detail 

Who 

Build Foundation 

Build dedicated pilot infrastructure 

ITI 

Configure Services 

IS Apps and ITI select up to 3 services for Pilot 

ITI, Apps 

 

ITI & IS Apps define and create application monitoring structure (Distributed Application) for the UniDesk service 

ITI, Apps 

 

ITI & IS Apps define and create Distributed Application for the Learn service 

ITI, Apps 

 

ITI & IS Apps define and create Distributed Application for the Finance service 

ITI, Apps 

Design Dashboards 

IS Apps consult IS Helpline (and others) on requirements for dashboards 

Apps, USD 

Build Dashboards 

ITI & Apps work with Microsoft to build dashboards 

ITI, Apps 

Pilot Dashboards 

Evaluation and test run with new dashboards 

ITI, Apps, USD 

Report 

Report on evaluation and build 

ITI, Apps 

 

NB where ITI/Apps is indicated as responsible, only Apps effort is accounted for in estimates.

The majority of Apps time is Production Management; it is anticipated that the effort split will be:

  • 70% Production Management,
  • 15% Dev ISG
  • 15% DevTech

(This represents approx 54 Days for Production Management, and 11.5 Days each for Dev ISG and DevTech, including project meetings).

However, these estimates will be reviewed when the dedicated pilot infrastructure has been built.

 

Resources Skills and Cost

This project is estimated as 120 days for IS Apps effort. 

It is proposed that effort on the project is planned according to the 95% confidence estimate.

Estimates will be reviewed during initial configuration.

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary