Organisation

 

Work/Task Breakdown

 

 Planning

*       Confirm Apps and ITI members of the team

*       Confirm commitment and “buy-in”

*       Confirm project brief with the project sponsor and project team

*       Prepare project estimates

*       Prepare project plan

*       Sign-off planning phase

 Business Analysis

*       Define requirements

*       Define model answers

*       Contact and arrange visits to matching universities

*       Assess and evaluate “fit”

*       Publish outcome and recommendation

*       Sign-off Business Analysis phase

Closure

*        Prepare closure report

*       close project

Resources Skills and Cost

Estimates up to point of finding best fit (Recommendation) will include;

60 days for Apps, 30 days for ITI, for analysis and assessment of other institutions' solutions. Trips to 4 institutions for a team of 3 Apps folk, rail fares, £5,000.

A budget of £30,000 is currently available to purchase a solution.

60 days leaves us 100 days in 13/14 plus available 40 days contingency.

A further 120 days plus another 40 days contingency planned for 14/15.

 

ITI will need to commit resources also, to help with analysis and to be on the site visits also. The estimate of 30 days for ITI above reflects this.