Impact

Priority and Funding

Normal. Sponsor funded.

Impact and Dependencies

Availability of key staff. Communication from Head of College to inform and influence and encourage the use of Simitive.  Academic engagement with the changes needed  around process and tools.  Engagement of Directors of Professional Services and their teams.

Dependent on Core Systems Implementation project for cutover to new HR system

Project Risks

Ref

Title

Initial Risk

Current Risk

Management Approach

Risk Owner

1

Existing business process do not match system behaviour

GREEN

GREEN

Reduce

Fraser Muir

2

Insufficient time for stakeholders to adopt new process for planning year.

GREEN

GREEN

Reduce

Matthias Schwannauer

3

Lack of Academic engagement

RED

RED

Reduce

Matthias Schwannauer

4

Not all Schools adopt the system.

AMBER

AMBER

Reduce

Fraser Muir

5

Stakeholder resistance to change

AMBER

AMBER

Reduce

Fraser Muir

6

Unavailability of key staff for adoption of the system

GREEN

GREEN

Reduce

Matthias SCHWANNAUER

7

School functional requirements not met by system

GREEN

GREEN

Reduce

Fraser Muir

8

New Business process is dramatically different to existing process in some Schools

GREEN

GREEN

Reduce

Fraser Muir

9

Risk due to proximity of delivery milestone to Core System delivery

AMBER

AMBER

Reduce

Fraser Muir

10

IS Apps Staff availability

RED

GREEN

Reduce

Muriel Mewissen

 

 

Project Info

Project
WAMS Business Embedding
Code
HSS031
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Fraser Muir
Current Stage
Analyse
Status
In Progress
Project Classification
Grow
Start Date
23-Sep-2019
Planning Date
10-Oct-2019
Delivery Date
31-Mar-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Plan