Report for September 2019
- Report Date
- September 2019
Achievements
- Pre-employment and Induction checklist content agreed and produced in Word Form template format.
- Scoping document reviewed and recommendations for future implementation proposed.
- Proposed project closure process raised with project sponsor.
Issues
Next Steps
- Checklists process documented and handed over to project .
- Project scoping document updated to include recommendations for implementation of outstanding actions.
- Project meeting held to review checklists and revised scoping/recommendation report.
- Project closure.
Milestones
Target Date![]() |
Title | Stage |
|---|---|---|
| 26-Jul-2019 | End of Planning | Plan |
| 02-Aug-2019 | Production of Scoping Report | Execute |
| 06-Sept-2019 | Initial Induction Updates - Delivered | Deliver |
| 20-Sept-2019 | Project Scoping/BAU Plan | Deliver |
| 04-Oct-2019 | Project Closure | Close |
- Approved budget
- 25.0 days
- Activity this month
- 2.4 days
- Activity this year
- 3.8 days
- Activity to date
- 22.7 days
- Estimate to complete current year
- 1.8 days
- Estimate to complete future years
- 0.0 days