Report for December 2015

Report Date
December 2015

The project has delivered and Closed as planned on 18/12/15

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
HR Transformation: Governance and Planning
Code
HRS088
Programme
Human Resources (HRS)
Project Manager
Susan Ridder-Patrick
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
08-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Dec-2015
Programme Priority
1
Overall Priority
Normal
Category
Compliance