Organisation

 

Work/Task Breakdown

  • Clone Dev 
  • Clone TEST

There will then be three phases

  • Phase 1 Prerequsite Patches ( likely Family Pack and including any available autoenrolment or RTI patches) 
  • Phase 2 Tax Year End (including any required autoenrolment or RTI patches), and Security Patches  and P60s Updates
  • Phase 3 Post Budget (including any required autoenrolment or RTI patches). This phase may not be required if no post budget changes are needed.

Each Phase will incororate

  • Investigation into work required for this Phase
  • Apply work to DEV and check out
  • Apply work to TEST and check out
  • Support Acceptance testing
  • Deploy to LIVE

Change required to the P60 form for 13/14 will also be made under this project. 

Resources Skills and Cost

Resources and Skills; 

  • HR, Payroll and Pensions will be required to test and sign off patching in each of the three environments. FIS support also likely to be required throughout the project. 
  • IS Applications Support Co-ordinator and IS Applications developer will review available patches and jointly agree what are to be applied.
  • IS Applications Technical Architect will be required to complete clone work and identify and apply security patches. 
  • IS Applications Developer will amend the P60 form as agreed with the Payroll Manager

Cost; 

  • no costs expected for this project
  • IS Applications days are covered by Core Funding

 

Project Info

Project
HR & Payroll Annual Maintenance 13/14
Code
HRS075
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
24-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
1
Overall Priority
Normal
Category
Compliance