eRecruitment Project Team Meeting (13/08/13)
eRecruitment Project Team Meeting (13/08/13)
Attendees
EDGAR Anna | |
KILGALLON Deborah | |
STUART Nikki | |
MCLAREN Susan | |
RUTHERFORD Katrina |
Meeting Notes
Meeting discussed the actions that are not covered by Jiras or support tickets.
It was noted that a missing notification had been reported in the last few days. This is a reoccurrence of, what was hoped, a closed issue. Jira has been passed to Nikki (post meeting update - Jira now with Garry).
It was noted that the next PB is 10th September. Need to provide paper for phase 2 plan and benefits review. It was agreed that;
§ it would be useful to hold a meeting early sept to discuss options for approach to benefits/efficiencies review with input from IS Apps "specialists"
§ the plan for phase 2 should start with;
· initial meeting with "new" team september
· review of previous requirements (both ITT and previous implementation projects) end sept, and
· core demo late October
Actions
Email Eoghan to confirm list of internal applicants to be reset MCLAREN Susan | 16 Aug 2013 |
Eoghan to agree date to reset internal applicants with Susan and Nikki STUART Nikki | 19 Aug 2013 |
Confirm dates with Eoghan for workflow update and search parameters bug fix STUART Nikki | 16 Aug 2013 |
confirm date for final phase 1b update (screen alignment) with Eoghan STUART Nikki | 16 Aug 2013 |
discuss with Eoghan that we will be removing test and live access STUART Nikki | 16 Aug 2013 |
Nikki to get Eoghan to confirm if can rename "at risk" STUART Nikki | 16 Aug 2013 |
chase boxi updates to allow access to the profile feilds STUART Nikki | 16 Aug 2013 |
Review dates and options to clone dev and test STUART Nikki | 21 Aug 2013 |
Arrange meeting to review lessons learned STUART Nikki | 19 Aug 2013 |
Arrange meeting to discuss options for benefits review study STUART Nikki | 21 Aug 2013 |