Auto-enrolment and P2 TYE , RTI update Update 28/02/13
Meeting Gillian, Alyson, Ana with updates from Greg and updated Nikki Thursday 28/02
Auto-enrolment
- Confirm AE signed off for LIVE - Kathy and Pamela have both signed off verbally (email down) on 28th Feb 13 - Monday 4th March
- Greg will complete patches in LIVE
- Ana will complete package in LIVE
- Then business will verify LIVE is complete for AE
P2 Tax Year End & Real Time Information
- HR Global being progressed in DEV - Now available and Kathy checking out that the 2 fields are correct in both environments before completing the basic tests. (28/02)
- DEV HR Global being verified, progress being made and the 2 fields that have been re-named related to SAP and SMP. These are recovery fields used as formula to reclaim SSP from HMRC. - Once DEV is available for Kathy to verify that TEST and DEV have the same results in them --Kathy verified that both SMP recovery-UoE and SAP recovery -UoE are at 92% and look fine in DEV
- Also Kathy will do basic testing in DEV before TYE and RTI are moved to TEST
- Plan is that P2 TYE + RTI will move to TEST on Tuesday 5th March.
- Before starting the patching Alyson will rename the 2 elements in TEST that require to be renamed first
- After Alyson has renamed the elements Greg will do the Patching to TEST
Wed/Thurs 6-7th March Susan and Kathy will complete testing to ensure the TYE and RTI information can be signed off to go LIVE on 11-12 March
Fri 8th March Business Signoff for TYE + RTI Preparation for Mon 11th March
Monday 11th March Downtime
Tuesday 12th March at Risk
Wednesday 13th March HR & Payroll P2 TYE & RTI Signoff