Background
This project is intended to deliver enhanced functionality with a number of improvements to the use of the Control of Substances Hazardous to Health Regulations (COSHH) Health Passport System (CHPS).
In addition, a feasibility study will be undertaken to consider the integration of Occupational Health related FitNote information from the eOPAS application and the effort required were it to be brought into the scope of the present project. The feasibility will consider the provision of data in CSV format as an alternative means to a fully automated solution.
Scope
The scope of the work will be allocated over four sprints with a review period at the end of each sprint to determine the future release date. All requirements identified to bring improvements to CHPS are documented as numbered 'Would Like' issues in a Jira backlog catalogue.
As part of the review process, decisions are taken on prioritisation as to which issues are to be included in a subsequent sprint. To this end, the order of work to be undertaken can change.
Sprint 1
22 - Collapse the notes section to a specific view
23 - Need Auto Note added on Exposure Record and PDF Upload
21 - School Safety Advisor (SSA) Dashboard - Update 'Health Surveillance Look ahead' title
20 - Rename SSA role - Area Coordinator
17 - Update the User Maintenance Admin Page
15 - Areas - Update the name - Central
02 - Users on Search Results - Facility Access Revoked
Sprint 2
03 - Specific notification emails for Facilities, currently all generic
04 - Specific notification emails for changes in record, for example if FitNote is uploaded, Face Fit Test (FFT)
29 - Supervisor dashboard - Supervisees with upcoming health surveillance title
25 - Rejection reason character set
10 - Edit function on pre-induction information
30 - Import capability for health service results
19 - Allow an individual to be a coordinator for more than one area
Sprint 3
07 - Multiple people risk assessment upload
08 - Multiple people generic document upload
14 - Ability to download management information data
11 - Health and Safety (H&S) Admin dashboard improvements
24 - Search function - remove area/facility options from SSA and Principal Investigator/Supervisor (PI/Sup) view
13 - Current issue with PI/Sup who have left but not been changed in system (Unidesk)
26 - Exit FitNote may be covered under requirement 30 (to be investigated)
18 - Adding a new user
Sprint 4
06 - New role for (Bioresearch & Veterinary Services (BVS) administration - include all SSA function but also able to add/edit Facility Managers
27 - Re-sending induction form eMails
28 - Functionality to add new facility
05 - Notification emails - review frequency and text
16 - FitNote edit function for Admin - delete/remove only
09 - Upload of Procedure Project Licence/Procedure Individual Licence (PPL/PIL)
12 - SSA dashboard - quick view figures links to actual lists
31 - Depreciation warnings in code
32 - Update system description document
33 - Change Health Passport system Error email subject on live
Objectives
The initial objective is to review all the known requirements to determine the level of complexity, effort involved and thereafter, prioritise development, testing and implementation effort into 'packets' of work. The wider objective is to reduce/clear as many of the open requests as possible within the project timeline and the allotted budget.
A secondary objective is to better understand what would be required to provide a technical solution to enable electronic data transfer of FitNote information. This is in preference to the present manual process that is followed. An alternative consideration will be the provision of data in CSV format and added as an issue to the backlog catalogue.
Deliverables
| Objectives and Deliverables | Priority | Owner |
| O.1 Understanding of business requirements | ||
|
D1.1 The succinct requirements will be translated from business terminology and acronyms into use stories |
Must | Business Analyst |
| D1.2 Use stories will be added to JIRA as a product backlog along with acceptance testing criteria | Must | Business Analyst |
| O.2 Work effort will be aligned with the Agile framework | ||
| D2.1 Work will be managed as multiple sprints aligned to project scope and covering cycles of development, testing and code release | Must | Project Team |
| O.3 Project documentation will be maintained for future use | ||
| D3.1 The System Description Document will be updated and included in the handover to IS Apps Production | Must | Developer |
| D3.2 The User Training material will be updated | Must | Projects Assistant |
| O.4 Compliance with Personal Information Guidelines | ||
| D4.1 Completion of a Data Protection Impact Assessment (DPIA) | Must | Project Sponsor |
| O.5 Assessment of FitNote Automation | ||
| D5.1 Engagement with 3rd party Supplier/business area currently undertaking manual creation | Must | Business Analyst |
| D5.2 Undertake a feasibility study on costs and timelines | Must | Business Analyst |
| D5.3 Integrate eOPAS generated FitNote | Could | Project Sponsor |
| O.6 Document all completed/outstanding work at project end | ||
| D6.1 Produce a project closure report | Must | Project Manager |
Benefits
During the current trialling of the system, feedback has mainly been positive but all criticisms have been logged and many will be addressed during this project. It is planned to roll out the system fully for the coming academic year and these improvements will ensure that staff and students are fully engaged in using it, which will reduce the overall risk to the University.
Functional changes to the COSHH Health Passport System are expected to enhance the end-users experience.
Success Criteria
Business use of the changed functions with no detrimental impact on the quality of the applications/service.
Project Milestones
| Stage | Milestone | Due Date | ||
|---|---|---|---|---|
| Initiate | Project Initiation | 22-Apr-2019 | ||
| Plan | Project Planned | 10-May-2019 | ||
| Accept | Sprint 1 Release Review Point (go/no go decision) | 08-May-2019 | ||
| Execute | Sprint 1 Complete | 16-May-2019 | ||
| Accept | Sprint 2 Release Review Point (go/no go decision) | 30-May-2019 | ||
| Execute | Sprint 2 Complete | 06-Jun-2019 | ||
| Accept | Sprint 3 Release Review Point (go/no go decision) | 20-Jun-2019 | ||
| Execute | Sprint 3 Complete | 27-Jun-2019 | ||
| Accept | Sprint 4 Release Review Point (go/no go decision) | 23-Jul-2019 | ||
| Execute | Sprint 4 Complete | 31-Jul-2019 | ||
| Deliver |
|
31-Jul-2019 | ||
| Close | Project Closed | 09-Aug-2019 |