Impact

Priority and Funding

Upgrading FPM from version v2.4.0.11 to the latest version, which would support resolution of both outstanding FPM penetration and post eFinancials v5.0 go-live testing issues. (see FIN128 Background section previously). The original decision, to postpone production deployment of the FPM module, was approved only after the FIN118 project team had gained agreement with the Information Security team, that FPM must be upgraded as soon as practically possible following eFinancials v5.0 go-live.

The overall project priority for FIN128 is NORMAL

The FIN128 project will be set-up as a Priority 1 project within the current Finance programme structure

This project will also be CORE funded

Impact and Dependencies

Impact:

  • Delivery of FIN128 objectives will improve the current system stability status of Finance Process Manager (FPM).
  • FPM is the main application used by University staff to support processing of non-PO related transactions such as new supplier requests and payment vouchers, which are not directly processed via eFinancials.
  • FIN128 should also resolve outstanding medium/low priority Penetration testing issues for FPM that were identified during the FIN118 project.

Dependencies:

  • The delivery of FPM release v2.4.0.16 from Advanced (supplier) should occur by March 15th, 2019
  • Suitable Development Technology resources will be assigned to FIN128 by the start of the FPM Build phase (March 2019).
  • Acceptance testing resources provided by the Finance department will be available to test from March 4th.

Project Risks

Ref: Title Initial Risk RAG Status Final Risk RAG Status Current State  Management Approach Risk Owner
1 The FPM software vendor's current development schedule for release v2.4.0.16 of FPM may be delayed beyond March 1st, 2019. Green Green Open Reduce Douglas Stewart
2 There may be significant FPM re-work identified during FIN128 UAT, based on UAT lessons learned from FIN118 Green Green Open Reduce Douglas Stewart
3 Finance department resources assigned to FIN128 UAT may be re-assigned to other SEP priorities during FY18/19. Green Green Open Reduce Douglas Stewart
4 Finance department resources assigned to FIN128 UAT may also be re-assigned to other Finance department priorities during FY18/19 Green Green Open Reduce Douglas Stewart
5 A new version of the Paperclip application may be released by Advanced with v2.4.0.16 of FPM. Green Green Open Reduce Leon Toland
6 That critical bugs identified with v2.4.0.16 of FPM may require resolution via additional FPM release/s Amber Amber Open Reduce Douglas Stewart

 

Project Info

Project
FPM Upgrade
Code
FIN128
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
21-Jan-2019
Planning Date
22-Feb-2019
Delivery Date
10-Dec-2019
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Compliance