eAuthorisations updates now Live |
The latest updates to the eAuthorisations application were deployed into the University's Live environment on Monday 20th July 2015.
This version of eAuthorisations delivers three distinct sets of business requirements: |
Jill Nicoll |
20-Jul-2015 |
|
Project update for w/e 10-July-2015 |
UAT sign-off confirmed.
Live deployment scheduled for 20-July-2015. |
Jill Nicoll |
10-Jul-2015 |
|
Weekly update w/c 27/04/15 |
- Build sign-off meeting held for workpackage 1 (eAuth/OpenAM interface automation)
|
Dawn Holmes |
01-May-2015 |
|
Weekly update w/c 20/04/15 |
- Project Brief was approved by WIS but on the condition that the project progresses according to the recommendations from the Architecture Group
- Feedback from Project Sponsor indicates that only workpackage will be completed within this project. The budget for the remaining workpackages will be transferred to the Launch Phase 2 project to fund resolution of the technical issues they're encountering
|
Dawn Holmes |
24-Apr-2015 |
|
Weekly update w/c 13/04/15 |
- Project Brief re-submitted to WIS following its rejection last week whent the PM was on leave
- Architecture Group advised of the proposed solution as recommended by WIS
- Catch-up held with developer to determine the status of the workpackage 1 development. Small change required to code for HTBN wording for another project, which will be undertaken early next week so that peer testing can take place on the final version.
|
Dawn Holmes |
17-Apr-2015 |
|
Weekly update w/c 30/03/2015 |
- Meeting held with other Project Managers on projects making changes to eAuthorisations (RES055 & HRS083) to agree how best to tackle the deployments
- Meeting held with Dev Tech to evaluate the impact of promoting eAuthorisations to live before FIN101 Launchpad Phase 2 is complete. It is currently thought that the impact will be minimal but additional testing will be required to check this.
|
Dawn Holmes |
03-Apr-2015 |
|
Weekly update w/c 23/03/2015 |
- No progress this week due to resource conflicts for developer and project manager
|
Dawn Holmes |
27-Mar-2015 |
|
Weekly update w/c 16/03/15 |
- No progress this week due to resource conflicts for developer and project manager
|
Dawn Holmes |
19-Mar-2015 |
|
Weekly update w/c 09/03/15 |
- The Project Sponsor has advised that Finance can work around the anomoly regarding eFIn users with no financial limits in eAuth. The result is that workpackage 1 design/development is acceptable and can be deployed to Test for UAT.
|
Dawn Holmes |
13-Mar-2015 |
|
Weekly update w/c 02/03/2015 |
- Response received from Finance re requirements for workpackage 1. The response has caused an issue as Finance wish to change the requirements and development has already been completed.
- Some requirements for workpackage 2 have been received but they are insufficient for design to begin.
|
Dawn Holmes |
06-Mar-2015 |
|
Weekly update w/c 23/02/2015 |
- Still no response from Finance regarding the sign-off of the Project Brief. A reminder has been sent.
- Still no response from Finance regarding the requirements for workpackage 2. A reminder has been sent.
- Development of workpackage 1 is complete and peer testing is underway
- Build review for workpackage 1 booked for next week
- Dev Tech have been requested for next week to deploy workpackage 1 to Test
|
Dawn Holmes |
27-Feb-2015 |
|
Weekly update w/c 16/02/2015 |
- Meeting held with Production Management and Dev Tech to discuss their involvement in the project
- Project Brief signed-off by IS Apps stakeholders but still waiting for reply from Finance.
- The Business Lead has been off sick this week so the formal planning sign-off will be delayed into next week. Work on workpackage 1 will continue in the meantime to avoid further delaying the project.
- Peer Testing for workpackage 1 is scheduled for next week
- Still no response from FInance regarding requirements for workpackage 2
|
Dawn Holmes |
20-Feb-2015 |
|
Weekly update w/c 09/02/2015 |
- Business requirements for workpackage 1 clarified and documented
- Tech set-up underway for workpackage 1
- Software development underway for workpackage 1
|
Dawn Holmes |
13-Feb-2015 |
|
Weekly update w/c 02/02/2015 |
- Planning meeting held with Software Development to review scope, risks and general approach
- First draft of Project Brief in progress
- Design for workpackage 1 in progress (N.B. it's unusual to start this work before the Brief is signed-off, but the developer only has a short period of availability and the requirements for this workpackage are clearly understood)
- Issues securing a Dev Tech resource to to the tech set up required for workpackage 1 build to start
|
Dawn Holmes |
05-Feb-2015 |
|
Weekly update w/c 26/01/2015 |
- Project Manager allocated
- Project website created
- Kick-off meeting held with Project Sponsor to discuss project scope, timescales and stakeholders
|
Dawn Holmes |
04-Feb-2015 |