Weekly update w/c 30/03/2015

  • Meeting held with other Project Managers on projects making changes to eAuthorisations (RES055 & HRS083) to agree how best to tackle the deployments
  • Meeting held with Dev Tech to evaluate the impact of promoting eAuthorisations to live before FIN101 Launchpad Phase 2 is complete. It is currently thought that the impact will be minimal but additional testing will be required to check this.

Project Info

Project
Launchpad phase 3 (eAuthorisations)
Code
FIN103
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Overall Priority
Normal
Category
Discretionary