Project journal

Title Description Author Post date
Weekly update w/c 27/07/2015
  • Outstanding issue with student fees payments for previous academic years now revolved & signed-off in Test
  • Outstanding ssue with transposed payment dates now resolved & signed-off in Test
  • Latest version of software deployed to Live
  • Project submitted for closure

 

Dawn Holmes 31-Jul-2015
Weekly update w/c 06/07/2015

Dawn Holmes 10-Jul-2015
Weekly update w/c 29/06/2015
  • Closure meeting held to review completion report and identify any remaining actions.
  • Potential issue raised with payments for previous academic years. Agreed to keep project open until clarified during loading of June payment.

 

Dawn Holmes 30-Jun-2015
Weekly update w/c 22/06/2015

  •  Project Sponsor confirmed that the project should close despite the issue with processing large files.  Project Sponsor will speak to her team to see what assistance can be offered to FSS to ease the additional manual effort of chopping up the large files.  A project proposal for a longer term solution will be added to the next planning round.
  • Draft completion report distributed for review
  • Meeting planned for early next week to review the completion report & sign-off project closure
Dawn Holmes 26-Jun-2015
Weekly update w/c 01/06/2015
  • Deployment sign-off from most parties - some still to respond
  • Decision required on how to approach the issue with processing large files.  3 options suggested to Finance & meeting booked for after the PM's return from annual leave to discuss further  

 

Dawn Holmes 05-Jun-2015
Weekly update w/c 18/05/2015
  • new application deployed to Live on Tuesday
  • first small file uploaded & posted into eFinancials for checking by Accounts Payable - 'all clear' given to load remaining payment files
  • timeout issues are reported to be much worse than in Test and files are having to be manually cut down to less than 1000 records.  This is a time consuming manual process so a resolution is needed before the next large file is due in June
Dawn Holmes 22-May-2015
Weekly update w/c 11/05/2015
  • The software developer has been working on a resolution to improve the sped of the interface to prevent it timing out but so far has not been able to improve it enough to resolve the issue.
  • Business partners have been contacted to decide whether to delay next week's go-live or to proceed with small files only.  The unanimous response was to proceed with the go-live and to pursue a resolution prior to project closure.
  • Resources have been requested for the go-live and a change control raised in preparation
  • The software developer has noticed that the allocation set
Dawn Holmes 15-May-2015
Weekly update w/c 04/05/2015
  • During final UAT an issue with large file was discovered whereby the interface is timing out & failing
  • Software developer has been booked for next week (w/c 11/05/2015) to investigate
Dawn Holmes 15-May-2015
Weekly update w/c 27/04/15
  • Meeting held with representatives from Accounts Payable, FSS and Financial Accounts to clarify the processes for credit notes and clawbacks.
  • Revised milestone dates agreed for live deployment.  Project records updated accordingly.
  • Process diagram updated & distrubuted for review
  • Developer booked for Monday next week to make final(?) change to the application for student numbers with leading zeros.
Dawn Holmes 01-May-2015
Weekly update w/c 20/04/2015
  • Further UAT undertaken this week which identified an issues with student  numbers with leading zeros (these are failing to load)
  • Key business lead is not in the office this week so decisions on how to proceed will have to wait until next week
Dawn Holmes 24-Apr-2015
Weekly update w/c 17/04/15
  • Further UAT undertaken this week.  All known issues are now resolved.
  • Accounts payable have requested a further meeting to discuss the process for handling credit notes & overpayments/clawback.  This meeting has been arranged for w/c 27th April
  • Planned go-live for this week has been cancelled until the above meeting has taken place
Dawn Holmes 17-Apr-2015
Weekly update w/c 30/03/2015
  • change completed to split large files into smaller batches of 500 rather than 1000.  This is now undergoing UAT
Dawn Holmes 03-Apr-2015
Weekly update w/c 23/03/2015
  • Resources secured to resolve deployment issue with 'our ref' change reported last week
  • Further issues found when trying to re-load test file so additiional resources had to be secured to resolve and re-deploy to Test
  • Further issues then found when trying to re-load the test file with file sizes over 700 records where the 'allocation ref' became corrupt.  Also test files are not loading as it reports the data doesn't match Test eFin, even though Finance have checked and confirmed that it does.
Dawn Holmes 27-Mar-2015
Weekly update w/c 16/03/15
  • Change to 'our ref' to remove 'BS' prefix deployed to Test
  • UAT by Finance conducted but failed as the prefix was still present.  Investigations suggest that there has been an issue with the deployment as this is working correctly in Dev.
  • Further resource secured for next Monday to investigate further & resolve
Dawn Holmes 19-Mar-2015
Weekly update w/c 09/03/15
  • Change to 'our ref' field content requested by Accounts Payable has been actioned and is ready to deploy to Test
  • Dev Tech resource requested to deploy change to Test for UAT but no resource currently available.  Hoping for availability on Monday so that UAT can be completed before the business rep goes on leave
Dawn Holmes 13-Mar-2015
Weekly update w/c 02/03/2015
  • Further UAT in Accounts Payable has uncovered another change required relating to the content of the 'our ref' field.  This is currently with Finance for clarification of what is required.
Dawn Holmes 06-Mar-2015
Weekly update w/c 23/02/2015
  • Large test file successfully loaded into eFinancials
  • 2 of the 3 fixes have been signed off, the third required further re-work
  • Further re-work completed and re-deployed to Test for final UAT next week
Dawn Holmes 27-Feb-2015
Weekly update w/c 24/02/2015
  • Changes requested by Accounts Payable deployed to Test
  • Additional test files loaded to check new funtionality and initial indications are good though not yet formally signed-off by Accounts Payable
  • Large data file for final test has been requested from FSS and is planned in for next week
Dawn Holmes 20-Feb-2015
Weekly update w/c 09/02/2015
  • Developer time secured to look at feedback from Accounts Payable
  • Requested changes now made to the application and Dev Tech secured for w/c 16/02/2015 to implement into Test for further UAT
Dawn Holmes 13-Feb-2015
Weekly update w/c 02/02/2015
  • Income Section did an initial test of the de-allocation of a single invoice line and confirmed that it worked ok.
Dawn Holmes 05-Feb-2015

Project Info

Project
SAAS/SLC Fees Reconciliation
Code
FIN094
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
16-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Programme Priority
2
Category
Compliance