Report for February 2014
- Report Date
- February 2014
Achievements this period
- Phase 2 part 2 (the historic feed) acceptance testing completed this month and was signed off by Finance, SACS and IS reps
- A go-live date of 11th March has been agreed to allow for the SITS upgrade to complete and the Business Object freeze to be lifted
Issues
- None currently
Next Steps
- Go-live is planned for 11th March
- Deployment review
| Target date | Title |
|---|---|
| 11-Mar-2014 | Phase 2 Go-live (part 2) |
| 25-Mar-2014 | Phase 2 - Deployment Review |
| 08-Apr-2014 | Closure |
- Approved budget
- 233.0 days
- Activity this month
- 4.8 days
- Activity this year
- 49.1 days
- Activity to date
- 229.1 days
- Estimate to complete current year
- 6.5 days
- Estimate to complete future years
- 0.0 days