Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 AMBER GREEN GREEN AMBER No Change
Report for November 2019 November 2019 AMBER GREEN GREEN AMBER No Change
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN No Change
Report for September 2019 September 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Estates Energy and Security windows server update
Code
EST127
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Karen Adamson
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
13-Sep-2019
Planning Date
25-Oct-2019
Delivery Date
30-Jan-2020
Close Date
21-Feb-2020
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.