Report for December 2019

Report Date
December 2019

Achievements this period

  • Resourcing secured to complete the estimation

Issues

  • Strike action has caused a backlog of work for Dev Tech, the earliest a booking could be made was 20/01/2020 to complete the vendor / application review for the estimate.

Next Steps

  • 3 point estimate to be agreed by the teams
  • Milestones and resources to be agreed
  • Planning sign off
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Strike action has also resulted in a two week delay in December, annual leave, and a backlog at the start of January 2020 for the Dev Tech resource. This has now been resourced to review the vendors and applications to complete the estimate. Now resolved for January.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
2.0 days
Activity this year
19.0 days
Activity to date
19.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates Energy and Security windows server update
Code
EST127
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Karen Adamson
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
13-Sep-2019
Planning Date
25-Oct-2019
Delivery Date
30-Jan-2020
Close Date
21-Feb-2020
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.