Impact

Priority and Funding

This is a normal priority core funded project

 

Impact and Dependencies

There are no current project dependencies.

Impact:

  • Not upgrading to Oracle 12c will result in an unsupported infrastructure from January 2020.
  • Clear guidance is required from Mass that the upgrade will not impact any applications (including customisations).

 

Project Risks

 

1 Risk that the external supplier costs may be incurred or exceed the initial estimate GREEN Reduce Derrick Matheson
2 Risk that performance issues may occur after the upgrade GREEN Retain Mark Lang
3 Risk that compatibility issues may occur with Archibus or some modules GREEN Retain Derrick Matheson
4 Risk that Estates resources may not be available for their tasks GREEN Reduce Derrick Matheson
5 Risk that IS Apps resources are assigned to a higher priority project GREEN Retain Paul Mcnulty

Project Info

Project
Estates Archibus database upgrade
Code
EST126
Programme
Estates General Programme (EST)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Karen Adamson
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
20-Sep-2019
Delivery Date
16-Mar-2020
Close Date
08-Apr-2020
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation

Plan