Organisation
Work/Task Breakdown
Methodology Stage | Standard Stage Sign-Off | Project Approach |
Planning | Approval by Project Manager, Project Sponsor and IS Applications Management Team | Prepare brief / plans and submit to WIS Create Request for Change for the project. |
System Analysis & Design | Peer Project Design Review (PPDR) | Review existing TAD for EBIS Update as necessary, or prepare from template if none is available. |
Build | Peer Project Build Review (PPBR) | Set up CF11 DEV, TEST and LIVE environments. Check synchronisation of EBIS On-line across environments with SVN. Back-up any existing EBIS on-line code changes in CF9 DEV, TEST environments. Copy EBIS On-line production code to CF11 DEV, and amend as necessary. Ensure CF11 DEV environment is functioning correctly. Test and fix EBIS On-line in CF11 DEV Peer Testing |
Integration | Peer Project Integration Review (PPIR) | Migrate EBIS On-line to CF11 TEST Ensure CF11 TEST environment is functioning correctly. Check EBIS On-line and access to data Update build document and build record, CMDB update |
Acceptance | Acceptance Sign-Off Review (ASOR) | Conduct UAT on CF11 EBIS On-line. Reports back any issues, agree appropriate remediation strategy, execute and test fixes in CF11 DEV as necessary, followed by re-deployment into CF11 TEST. Production Management to create Deployment Checklist. |
Deployment | Deployment Sign-Off Review (DSOR) | Create service alert 2 weeks prior to deployment to LIVE Migrate EBIS On-line to CF11 LIVE on or before specified date. Change load balancers to point to new CF11 LIVE Confirmation of successful deployment by business users. Deployment sign off Restore any saved EBIS On-line code changes into CF11 DEV ansd CF11 TEST environments. |
Closure | Closure Review and Approval by Project Manager, Project Sponsor and IS Applications Management Team | De-commission EBIS On-line in CF9 DEV, TESt and LIVE environemnts. Closure report and submit to WIS |
Resources Skills and Cost
Estimate 49 days:
Project Services (17.5 days)
Software Development (8.5 days)
Development Technology (13.1 days)
Production Management (3.4 days)
Meetings and discussions, all teams (6 days)