Organisation

Work/Task Breakdown

Work task breakdown is as follows:

  1. Planning

    • Prepare project brief incorporating:

      1. Project estimate

      2. Project plan

  2. Business Analysis

    • Document business requirements associated with additional functionality associated with:

      1. Missed collections

      2. Label Generation

    • Review and update existing test script

  3. Phase 1 Design

    • Update TAD

  4. Phase 1 Build

    • Provide a copy of the live system to FalconData

    • Falcondata to complete update locally and complete initial testing using UoE test script

    • Implement system upgrade with regards to:

      1. Database

      2. Windows client

      3. Web based portal

      4. New reporting module

  5. Phase 1 User Acceptance Testing

    • Repoint PDA's to test environment

    • Waste Management team to undertake user acceptance testing

    • Complete Deployment CheckList

    • Complete Operational procedures

    • Complete handover to IS Apps Production

    • Prepare deployment to live procedures, including fall back procedures

  6. Phase 1 Deployment

    • Back ups for go live

    • Deployment to Live

  7. Phase 2 Design

    • Update TAD

  8. Phase 2 Build

    • Provide a copy of the live system to FalconData

    • Falcondata to complete update enhancements locally and complete initial testing using UoE test script

    • Implement system enhancements with regards to:

      1. Database

      2. Windows client

      3. Web based portal

      4. New reporting module

  9. Phase 2 User Acceptance Testing

    • Repoint PDA's to test environment

    • Waste Management team to undertake user acceptance testing

    • Complete Deployment CheckList

    • Complete Operational procedures

    • Complete handover to IS Apps Production

    • Prepare deployment to live procedures, including fall back procedures

  10. Phase 2 Deployment

    • Back ups for go live

    • Deployment to Live

  11. Project Closure

    • Complete project closure report

    • Project closure

 

Resources Skills and Cost

The project will require the following resources:

  • Dev Tech - provide technical support throughout the project
  • Production Management - to oversee transition into the live environment
  • System supplier, FalconData - to deliver upgrade (and enhancements if time allows)
  • Fleur Ruckley, Waste Management Manger - to oversee and sign off all functional testing
  • Project Services - to manage the project

Project Info

Project
Waste Management System Upgrade
Code
EST090
Programme
Estates General Programme (EST)
Project Manager
Elaine Wighton
Project Sponsor
David Brook
Current Stage
Build
Status
Withdrawn
Start Date
03-Dec-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Discretionary