Organisation
Work/Task Breakdown
Planning
- Confirm project brief with the project sponsor and the project team incorporating
- project estimate
- project plan
- Secure resource bookings within ASTA
- Sign off planning phase
System Design
- Produce updated Technical Architecture Document
- Sign-off system design phase
Build Phase - Phase 1
- Prepare test script
- Confirm that the existing Test system is functioning as expected using the prepared test script
- Update test system to version 4.08
- Sign-off build phase 1
User Acceptance - Phase 1
- Complete user acceptance testing to ensure that the system is functioning as expected and new drawings are viewable
- Update Operations Document
- Complete Deployment Check List
- Complete handover to IS Applications Production
- Sign-off User Acceptance Testing Phase 1
Deployment - Phase 1
- Update Live system to version 4.08
- Confirm system functioning as expected
- Sign-off deployment phase 1
Build Phase 2
- Implement the new licensing model on Test
- Removal of network dongle on Test
- Confirm system connectivity
User Acceptance - Phase 2
- Complete user acceptance testing to ensure that the system is functioning as expected and new drawings are viewable
- Update Technical Architecture Document
- Update Operations Document
- Complete Deployment Check List
- Complete handover to IS Applications Production
- Sign-off User Acceptance Testing Phase 2
Deployment - Phase 2
- Implement the new licensing model on Live
- Removal of network dongle on Live
- Coordinate Live environment for DR test
- Complete DR test on the Live environment including return to the primary site
- Sign-off deployment phase 2
Closure
- Prepare closure report
- Review and approve project closure
- Sign off closure
Resources Skills and Cost
Resources wiill be required from the following teams;
- Estates and Buildings Energy Team to oversee all system testing
- IS Development Technology to provide technical assistance to Schneider enginners, update all technical documentation, overseee DR testing and provide handover to IS Applications Production
- IS Applications Applications Management to complete the Deployment check list
- IS Technical Management to oversee DR testing on Live