Organisation

 

Work/Task Breakdown

 

Planning

  • Confirm project brief with the project sponsor and the project team incorporating
    • project estimate
    • project plan
  • Secure resource bookings within ASTA
  • Sign off planning phase

System Design

  • Produce updated Technical Architecture Document
  • Sign-off system design phase

Build Phase - Phase 1

  • Prepare test script
  • Confirm that the existing Test system is functioning as expected using the prepared test script
  • Update test system to version 4.08
  • Sign-off build phase 1

User Acceptance - Phase 1

  • Complete user acceptance testing to ensure that the system is functioning as expected and new drawings are viewable
  • Update Operations Document
  • Complete Deployment Check List
  • Complete handover to IS Applications Production
  • Sign-off User Acceptance Testing Phase 1  

Deployment  -  Phase 1

  • Update Live system to version 4.08
  • Confirm system functioning as expected
  • Sign-off deployment phase 1

 Build Phase 2

  • Implement the new licensing model on Test
  • Removal of network dongle on Test
  • Confirm system connectivity

 

 User Acceptance - Phase 2

  • Complete user acceptance testing to ensure that the system is functioning as expected and new drawings are viewable
  • Update Technical Architecture Document
  • Update Operations Document
  • Complete Deployment Check List
  • Complete handover to IS Applications Production
  • Sign-off User Acceptance Testing Phase 2

 

Deployment - Phase 2

  • Implement the new licensing model on Live
  • Removal of network dongle on Live
  • Coordinate Live environment for DR test
  • Complete DR test on the Live environment including return to the primary site
  • Sign-off deployment phase 2

Closure

  • Prepare closure report
  • Review and approve project closure
  • Sign off closure

 

  

Resources Skills and Cost

 Resources wiill be required from the following teams;

  • Estates and Buildings Energy Team to oversee all system testing
  •  IS Development Technology to provide technical assistance to Schneider enginners, update all technical documentation, overseee DR testing  and provide handover to IS Applications Production
  • IS Applications Applications Management to complete the Deployment check list
  • IS Technical Management to oversee DR testing on Live

 

Project Info

Project
Schenider Sigma BEMS Upgrade
Code
EST081
Programme
Estates General Programme (EST)
Project Manager
Neil Grant
Project Sponsor
Dougie Williams
Current Stage
Close
Status
Closed
Start Date
01-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jan-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary