March Progress Report

Report Date
March 2014

Achievements this period

Considerable progress has been made during the last reporting period, both in terms of the overall infrastructure configuration and user testing.

With regards the infrastructure, having identified the need for the supplier, METERology to have remote and in some cases unsupervised access, whilst maintaining meters associated with the system, agreement was reached with regards

  • The overall technical design for the Meterology application
  • The method of remote access to configure the server
  • Locating the METERology system on the same private network recently installed for the BEMS server, to minimise any production concerns regarding remote access
  • Approval  of  the revised  Technical Architecture Document  (TAD)
  • The installation of the LIVE METERology server onto new private network

      

 User testing to-date has been successful in establishing

  • Remote access requirements confirmed for the supplier METERology, Estates and IS Apps 
  • Identified that a number of the more modern meters could be directed to both the current and new environment without any data loss
  • Completed a successful parallel test of the meter readings being processed by both existing and new system
  • In the event, of a full blown disaster, requiring the METERology system being located to a secondary site, the following activity was undertaken
    • Created Disaster Recovery Plan
    • Completed a successful test with the new METERology system running on a newly created server at the secondary site
    • Completed a successful failover back to the primary location
    • As a result, the Disaster Recovery milestone was subsequently achieved on 2nd April 

Issues

  •  No issues to report

Next steps

  Complete the remaining activity associated with the Live deployment, name

  • Review and ensure project accompanying documentation (e.g. Operations Document, Implementation Plan) is complete
  • Migrate existing database onto new environment
  • Ensure all meters directed to the METERology system on the new environment
  • Complete Deployment Sign off review and Closure

 

 Projected Milestones 

Dates 
4 Apr-2014Disaster Recovery
16-Apr-2014Deploy
30-Apr-2014DSOR and Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
62.0 days
Activity this month
18.0 days
Activity this year
52.0 days
Activity to date
52.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Meterology Metering System Migration
Code
EST076
Programme
Estates General Programme (EST)
Project Manager
Anne Mathison
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
21-Nov-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
29-May-2014
Programme Priority
5
Overall Priority
Normal
Category
Discretionary