Pre & Post Deployment Tasks
Pre - Deployment Tasks
- Agree outage time - 10.00am start time for deployment as confirmed by Project Sponsor
- Service Alert resubmitted for 26/11/13
- Change Record - raised on 05/08/13 Record Number 78427
- Deployment Checklist
- Implementation Tasks - WIP being updated in the deployment tasks below
- Access to FireAct Channel via MYED
- Create User Roles / Dashboards in LIVE
- Remove / Add CAD and Space Users - complete
- Review and update group members to SAMBA drive - complete
- EBIS User Communcation issued re: Outage 18/11 and Reminder issued 22/11
- Space management updated web pages
- Fire Drawings Procedures updated
- Space Management procedures updated
Post Deployment Tasks
- Communication to Space Contacts
- Updated procedures
- Rollout of Space Management module to Space Contacts community - agreed process by Space Managers
- Changes to Space Management web pages - copy received
- Update probtype table with current Live Problem Types - BREAKDOWN/PREVENTIVE MAINTENANCE
Deployment Tasks for LIVE (work in progress v0.8 uploaded 22/11/13)