Deployment

Deployment Strategy

Proposed Live deployment Wednesday 9th September 10am.

Full day outage will be required to perform the upgrade.

Holding pages will be put up for EBIS Online, WebCentral and FireAct MyEd channels. Users of Archibus will be reminded not to access the system on the day and time of deployment.

Cron Jobs will be disabled.

The database will be backed up prior to upgrade.

Apps Management will perform checks after upgrade.

Business will then perform testing before removing holding pages and allowing access for end users.

Full day At Risk up until the end of the following day

Dependencies

No dependencies on other systems. Service Alerts have been checked also to ensure no conflicts will occur on the deployment date.

Communication

Estates to communicate to EBIS_Online, ARCHIBUS, WebCentral and FireAct Channel users of the downtime.

Deployment Checklists

Application checklist 

 

Component

Success Criteria

Project Stage Required (Agile)

Ok (Y/N)

Reviewed By (Date)

Outstanding Actions (Who)

Implementation Plan

Feedback from previous test implementations completed and successful full implementation undertaken for UAT.

Implementation Plan to be updated by Martin Matt and reviewed by Gordon McKenna.

DSOR (Release 1-n)

 

John Chan/Anne Finnan

19/08/2013

Martin Matt from MASS to update. Gordon McKenna to review.

Implementation Risk Assessment

A risk assessment has been undertaken for the Implementation Plan and selected deployment dates. (e.g. roll back)

Restore of database and application files

ASOR (Release 1-n)

Y

John Chan

 

System Design Specification (SDS)

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

Deployment and Specification document received from MASS for Dev and Test.

 

 

ASOR (Final Release  / Handover)

N

John Chan

LIVE deployment document to be provided by 19th Nov  from MASS.

System Description Document

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

ASOR (Final Release  / Handover)

N/A

John Chan

 

Scalability/Load Testing

Adequate load testing has taken place. The results have been recorded and analysed to ensure that the application will cope with the anticipated load.

Not to be done as currently only low numbers of concurrent users expected.

ASOR (Final Release  / Handover)

N/A

John Chan

 

Performance

The application has been tested against stated performance criteria. Performance has been assured by user and support staff testing.

No performance issues encountered during UAT. There had been network issues but these seem to be resolved now.

ASOR (Final Release  / Handover)

Y

John Chan

 

Source Code

 

Source control must be checked out till go-live and checked-in after go live

Source code has been secured with VSS or other source control tool.

Where code is provided by a third party (e.g. supplier) it has been established who is responsible to maintain source code

Third party code.

Installation files will remain on the app and database servers.

DSOR (Final Release  / Handover)

Y

John Chan

 

Configuration Management Database

The relevant details regarding new or changed infrastructure components have been added to the configuration management database (This is currently maintained in the Change Control System)

No new or change infrastructure components introduced. WebCentral - Leasing Module service continued to be used.

ASOR (Release 1-n)

Y

John Chan

19/08/2013

 

 

Change Control(s)

A change control entry has been created for the LIVE implementation request.

1) Change Control for SAMBA Drive 78407 - 5th August 2) Change control for LIVE Deployment of Web Central Upgrade 78427 - 4th September

ASOR / (Release 1-n)

Y

John Chan

19/08/2013

 

Test Log Review

A review of the test log (JIRA) has taken place to ensure all required actions have been completed.   If this is not the case, then confirmation on criticality of outstanding issues and action plan for resolution is required.

Jira to be reviewed prior to Go Live.

ASOR (Final Release  / Handover)

Y

John Chan

19/08/2013

 

Production Management Handover

Handover to Production Management is completed and the team are in are in position to support the application post deployment.

ASOR (Final Release  / Handover)

Y

John Chan

19/08/2013

 

Support Accounts

Read access accounts or update current read access accounts have been set up for support staff(requires business owner approval)

No new accounts set up for upgrade.

ASOR (Final Release  / Handover)

Y

John Chan

19/08/2013

 

Password Manager (InfoKeep)

InfoKeep has been updated with all relevant account details including external supplier  accounts

 

No new accounts set up for upgrade.

ASOR (Release 1-n)

Y

John Chan

19/08/2013

 

 

Environment comparison

Database comparison between TEST and LIVE (might be required before and after go-live)

ASOR (Final Release  / Handover)

N

John Chan

19/08/2013

Gordon McKenna to perform on day of Go Live while Apps Mgmt perform checks.

Client requirements

 

Does the application have specific client requirements, such as JVM/JRE versions, JInitiator?

If so have these requirements been raised with Desktop services

Wiki pages to be updated:

[1] https://www.wiki.ed.ac.uk/display/insite/Corporate+applications+with+client+based+requirements

[2] https://www.wiki.ed.ac.uk/display/insite/Client+side+requirements+for+corporate+applications

No new specific client requirements caused by the upgrade.

ASOR (Release 1-n)

N/A

John Chan

19/08/2013

 

Technologies

Is there any new software or technologies involved? (Y/N)

If yes state any additional actions taken to ensure adequate handover to the production support team

No new software or technologies involved.

ASOR (Release 1-n)

N/A

John Chan

19/08/2013

 

Access outside University

By default all web based applications are accessible outside University without use of VPN etc Wiki list

If not accessible from outside University this needs to be approved by Production Management.

No change to existing set up. Web Central continues to be accessible outside university without use of VPN.

ASOR (Release 1-n)

Y

John Chan

19/08/2013

 

Certificates

All changes to certificates or new certificates for this service have to be added to the certificate master list. The certificate master list is being managed by Applications Management This includes TEST and LIVE certificates and records type of certificate and expiry dates.

No change to existing set up.

ASOR (Final Release  / Handover)

N/A

John Chan

19/08/2013

 

 

Infrastructure checklist

 

Component

Success Criteria

Project Stage Required (Agile)

Ok (Y/N)

Reviewed By (Date)

Outstanding Actions (Who)

Technical Architecture Document(TAD)

Documentation complete and accurately reflects the environment subjected to UAT.

 

Action: TAD needs to be copied to Wiki

ASOR (Release 1-n)

N

John Chan

Gordon to produce

Operational Document

Describes fully operational tasks and ongoing maintenance.This document should be fully populated and any missing sections or issues should be highlighted.

 

Action: TAD needs to be copied to Wiki

ASOR (Release 1-n)

N

John Chan

Gordon to produce

Security

All security requirements, e.g. SSL encryption, IP based restrictions firewall requirements have been specified, tested and implemented in LIVE

As per existing Web Central set up.

ASOR (Release 1-n)

Y

John Chan / Chris Cord

23/08/2013

 

 

 

 

 

 

 

Patching

Ensure that all applications have an agreed patching schedule and this schedule is agreed with service owners. Different technologies have different patching strategies:

Oracle, Windows, Linux

ASOR (Final Release  / Handover)

Y

John Chan / Chris Cord

23/08/2013

 

 

Infrastructure diagrams

All infrastructure diagrams are updated with newest server and infrastructure detail:

 

https://www.wiki.ed.ac.uk/display/insite/Server+Layout+%28Unix%29

 

and

 

https://www.wiki.ed.ac.uk/display/insite/Server+Layout+%28Windows%29

No change to existing setup.

ASOR (Release 1-n)

Y

John Chan / Chris Cord

23/08/2013

 

Start/Stop scripts

Are Server Start-up/Shutdown scripts in place?

Including start-up procedure documented, enabled and tested.

As per existing Web Central set up.

ASOR (Release 1-n)

Y

John Chan / Chris Cord

23/08/2013

 

Ports

Port allocation file been updated:

 

https://www.wiki.ed.ac.uk/display/insite/Port+Allocation+on+Unix+Servers

As per existing Web Central set up.

ASOR (Release 1-n)

Y

John Chan / Chris Cord

23/08/2013

 

Backup and Recovery

All backups as noted in the TAD need to be confirmed operational.

 

A test recovery of user data needs to be done to validate the integrity of the recovery mechanism and process.

As per existing Web Central set up. No need to perform recovery thereforre.

ASOR (Release 1-n)

Y

John Chan / Chris Cord

23/08/2013

 

DR Copy

DR copy to Edzell configured and tested(unless existing database which is already setup).

 

As per existing Web Central set up.

ASOR/Release1

Y

John Chan / Chris Cord

23/08/2013

 

Logs

For all logs the following is in place:

  • Logs are rotated and old logs are archived or deleted to ensure server space is not reached
  • In production only minimal levels of logging is switched on (debug may be adequate on DEV, but not on Production)

 

As per existing Web Central set up.

ASOR (Release 1-n)

Y

John Chan / Chris Cord

23/08/2013

 

 

 

Support checklist

 

Component

Success Criteria

 Project Stage Required (Agile)

Ok (Y/N)

Reviewed By (Date)

Outstanding Actions (Who)

Support Agreement (including any charging arrangements)

 

A support agreement (SLA or OLA) is in place for any new applications – including any hosting or support charges.

 

Action: SLA moved to wiki:

 

https://www.wiki.ed.ac.uk/display/insite/SLA+repository+-+Applications+Management

 

SLA for Estates in progress. Application Management will complete this document outwith this project.

ASOR (Final Release  / Handover)

Y

John Chan

19/08/2013

 

Time Recording Code

A Time Recording code for the application, if required, has been confirmed and set up.

Existing ESTS01  to be used.

ASOR (Final Release  / Handover)

Y

John Chan

19/08/2013

 

Disaster Recovery and Business Continuity

Appropriate DR/BC provision is in place and has been fully tested. Application DR/BC details have been transferred to the DR Portfolio and DR level (1, 2 or 3) has been agreed

As per existing Web Central set up.

ASOR (Release 1-n)

Y

John Chan

23/08/2013

 

Test Environment

An adequate TEST environment has been established for the application which may be used by support to test future changes prior to releasing these in the LIVE environment.

Yes. As per existing Web Central set up.

ASOR (Release 1-n)

Y

John Chan

23/08/2013

 

Hardware and Software Licensing

All required licensing is in place including maintenance/support arrangements with external suppliers.

As per existing Web Central set up

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Browser Compatibility

Browser compatibility has been tested and compatibility information updated

See

http://www.ed.ac.uk/schools-departments/information-services/services/computing/application-development/application-support/supported-web-browsers/browser-application

 for details

Application not compatible with IE10 - Application Management already aware/ Compatibility up to FireFox 23

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Portal Compatibility

Portal compatibility, where required, has been confirmed the Portals Service Owner.

As per existing Web Central set up. Web Central launch channel tested.

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Help Desk

The new application is recognised with the UniDesk (A business contact queue is defined where initial calls are raised with)

As per existing Web Central set up. Initial contact will be to EBIS team.

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

User Guide Documentation

Appropriate documentation has been produced for users of the new application.

Space Managers G Nicoll / R Mann responsible for updated procedures for Space Contacts. Archibus Product Overview documentation available.

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Training Material

Training material, if required, has been produced and is of an appropriate standard.

Space Managers G Nicoll / R Mann responsible for training material. Document produced for UAT.

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Demonstration or Walkthrough

Demonstration or walkthrough of the new application has taken place for other stakeholder.

Space Contacts have received training sessions.

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Deployment Date(s)

Agreed date has been confirmed that allows adequate time for completion of Acceptance Sign Off Review.

See Deployment Strategy at top of this document for Go-Live date.

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Deployment Resources

IS and business area resources required for deployment, including those needed for post implementation checking and sign off have been secured.

Dev Tech: G McKenna Apps Management: John Chan Tech Management: Chris Cord MASS: Martin Matt EBIS Support: Pauline Smith / Jane Cooney Space Managers: Gillian Nicoll / Richard Mann / Lisa Drysdale / Liz Torrance

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Deployment Ownership

Responsibilities for managing the go-live, including: comms with service owner and end users, ensuring go live timescales are met, managing issues arising and managing comms between all teams involved in go live.

Andy Stewart will be handling the Go Live deployment.

 

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

Service Announcement(s)

A Service announcement has been raised with the agreed deployment date on the alert system:

 

http://reports.is.ed.ac.uk/alerts/

 

Service announcements should be raised by Project Manager 10 days before go live, but no later than 4 days.

http://reports.is.ed.ac.uk/alerts/index.cfm?fuseaction=view_alert&alert_id=3144

ASOR (Release 1-n)

Y

John Chan

23/08/2013

 

Web Sites and Other Document Sources

External and internal web sites have been reviewed to ensure that all application references are present, correct and up to date.

Space Managers G Nicoll / R Mann responsible for web sites changes relating to Space Audit procedures etc

http://www.ed.ac.uk/schools-departments/estates-buildings/what-we-do/space-management/about-the-process

https://www.wiki.ed.ac.uk/display/insite/WebCentral has been updated.

 

ASOR (Final Release  / Handover)

Y

John Chan

23/08/2013

 

 

 

 

Project Info

Project
Space Audit Upgrade
Code
EST063
Programme
Estates General Programme (EST)
Project Manager
Karen Stirling
Project Sponsor
Maureen Masson
Current Stage
Close
Status
Closed
Start Date
16-Nov-2010
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2014
Overall Priority
Normal
Category
Compliance