Implementation Tasks

 

Qliksense

  1. Infrastructure Components

Servers built for DEV, TEST & LIVE by ITI, Alister Webb & Simon Minifie

ADFS deploy to LIVE

ADFS already configured in DEV and TEST Qliksense environments

 

ADFS implementation steps:

1] QlikIT - Simon Minifie - supply Qliksense proxy metadata file

( can only be provided as a file )

2] ITI - Neil Cooper - Create new ADFS service provider / configure the new ADFS service for Qliksense

3] IS Service Management - Andrew McFarlane - Enable users to grant access to Qliksense

 

Steps 1] and 2] can be done in advance - the new Qliksense service is not available until step 3] is done.

 

It is proposed that Qliksense will only be rolled out to a small number of  Pilot users in GASP - as first step of LIVE rollout

 

Data sources:

Qliksense - access to local file shares . All the file shares should be available via the login to the remote Terminal services server - same user login

Qliksense access to EDW

  1. Application Components

Determined by IS Service Management via permissions set in AD groups and within QMC ( Qlik Management Console) 

  1. Application Setup

Determined by IS Service Management via permissions set in AD groups and within QMC ( Qlik Management Console) 

  1. Integration Components

  2. Data Population

  3. Data Migration

  4. Implementation Validation

 

Qlikview

 

  1. Infrastructure Components

Windows 2016

Qlikview server

Qlikview remote Terminal services VDI service - Qlik-dash-remote - already installed by QlikIT ( Simon Minifie) - now needs testing

Qlikview - access to local file shares . All the file shares should be available via the login to the remote Terminal services server - same user login

Qlikview access to EDW

  1. Application Components

  2. Application Setup

  3. Integration Components

  4. Data Population

  5. Data Migration

  6. Implementation Validation

 

Project Info

Project
Qlik Implementation
Code
DTI034-1
Programme
Digital Transformation - BI Tools (DTIP08)
Management Office
ISG PMO
Project Manager
James Thin
Project Sponsor
Susan Cooke
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
13-Aug-2018
Planning Date
23-Nov-2018
Delivery Date
22-Nov-2019
Close Date
28-Feb-2020
Programme Priority
3
Overall Priority
Normal
Category
Discretionary