Organisation
Work/Task Breakdown
Planning (DTI015 Project) |
Produce Project Brief |
Agree estimates |
Planning Review / Sign-off Project Brief |
API |
Design |
Update TAD |
Update Application and Data Architecture Document |
Update System Description Document |
Design Review |
Build - Read-only |
Build Review |
Build - write |
Build Review |
Build - validation |
Build Review |
Integrate |
Integration Review |
Accept |
Acceptance Review |
Delivery |
Deploy to Live |
Handover to Production Management and Service Management |
Deployment Support |
Delivery |
Closure (DTI015 Project) |
Deployment Review |
Closure Report |
Close |
The Project Plan is here.
Resources, Skills and Costs
Resources from the following teams are required to deliver this project:
- Project Services
- Development Technology
- Software Development
- Enterprise Architecture
- Service Management
- Applications Management
- Technology Management
- Student Systems
The project is funded from the Digital Transformation Portfolio and has 90 days allocated within 2016/17 (see PRICCL Change 4 for summary). The project estimates are here.
Project Governance
Project Sponsor will provide direction.
Project Manager will manage the project on a day to day basis.
The Programme Steering Group terms of reference is below.