Organisation

Work/Task Breakdown

Planning (DTI015 Project)
   Produce Project Brief
   Agree estimates
   Planning Review / Sign-off Project Brief
API
   Design
      Update TAD
      Update Application and Data Architecture Document
      Update System Description Document
      Design Review
   Build - Read-only
      Build Review
   Build - write
      Build Review
   Build - validation
      Build Review
   Integrate
      Integration Review
   Accept
      Acceptance Review
   Delivery
      Deploy to Live
      Handover to Production Management and Service Management
      Deployment Support
      Delivery
Closure (DTI015 Project)
   Deployment Review
   Closure Report
   Close

 

The Project Plan is here.

Resources, Skills and Costs

Resources from the following teams are required to deliver this project:

  • Project Services
  • Development Technology
  • Software Development
  • Enterprise Architecture
  • Service Management
  • Applications Management
  • Technology Management
  • Student Systems

The project is funded from the Digital Transformation Portfolio and has 90 days allocated within 2016/17 (see PRICCL Change 4 for summary).  The project estimates are here

Project Governance

Project Sponsor will provide direction. 

Project Manager will manage the project on a day to day basis.

The Programme Steering Group terms of reference is below.

enterprise_apis_steering_group_tor_0.3.pdf

Project Info

Project
Student Record APIs
Code
DTI015
Programme
Digital Transformation - Enterprise APIs (DTIP03)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
03-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Sep-2017
Programme Priority
1
Overall Priority
Highest
Category
Discretionary

Documentation

Plan