Core Systems - Data Migration Project
Core Systems - Data Migration Project
Home
Projects
Core Systems - Data Migration Project
Current project status
Report Date
RAG
Budget
Effort Completed
Effort to complete
December 2019
AMBER
0.0 days
0.0 days
0.0
Outline
Core Systems - Data Migration Project
Project Approach Document
Project Approach Document ›
This article was published on
Jan 22, 2020
Project Info
Project
Core Systems - Data Migration Project
Code
COR004
Programme
Service Excellence - Core Systems (SEPCOR)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Jennifer Milne
Current Stage
Plan
Status
In Progress
Start Date
27-Nov-2018
Planning Date
15-Nov-2019
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
More project information
Documentation
Initiate
No documents
Plan
Project Approach Document
Execute
No documents
Deliver
No documents
Close
No documents
Other
No documents
Project Dashboard
View dashboard
Reporting
December 2019
November 2019
September 2019
review all
Project journal
No entries found.
more news
Change dashboard
Nothing to report.
review all