Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 AMBER 0.0 days 0.0 days 0.0 Content Status In Progress Current Stage Plan Start Date Tuesday, 27 November 2018 Planning Date Friday, 15 November 2019 Project information Project Code COR004 Programme Service Excellence - Core Systems (SEPCOR) Session 20/21 19/20 18/19 Organisational Unit IS Applications Project Management Office (if relevant) ISG PMO Responsibility SEP IT Overall Priority Normal