Current project status
Report Date
RAG
Budget
Effort Completed
Effort to complete
September 2018
GREEN
30.0 days
15.3 days
1.0
Outline
JIRA Upgrade
Project Brief
Overview
Impact
Organisation
Closure Report
Project Proposal
Project Brief ›
This article was published on
Jul 16, 2019
Project Info
Project
JIRA Upgrade
Code
COM040
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jun-2018
Planning Date
29-Jun-2018
Delivery Date
28-Aug-2018
Close Date
05-Oct-2018
Programme Priority
5
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Initiate
Project Proposal
Plan
Project Brief
Execute
No documents
Deliver
No documents
Close
Closure Report
Other
No documents
Project Dashboard
View dashboard
Reporting
September 2018
August 2018
July 2018
review all
Project journal
Annual upgrade of JIRA successfully completed
08-Oct-2018
more news
Change dashboard
Nothing to report.
review all