Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for September 2018 September 2018 GREEN GREEN GREEN GREEN No Change
Report for August 2018 August 2018 GREEN GREEN GREEN GREEN No Change
Report for July 2018 July 2018 GREEN GREEN GREEN GREEN
Report for June 2018 June 2018 GREEN GREEN GREEN GREEN
Report for May 2018 May 2018 AMBER AMBER

Project Info

Project
JIRA Upgrade
Code
COM040
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jun-2018
Planning Date
29-Jun-2018
Delivery Date
28-Aug-2018
Close Date
05-Oct-2018
Programme Priority
5
Overall Priority
Normal
Category
Compliance

Documentation