Organisation
Work/Task Breakdown
Phase 1 developments and activities
Business requirements – Application Management / Service Management
Development by Development Team, includes an implementation plan
Create and document UAT TEST Scenarios - Service Management
Document a TEST Plan – Application Management / Service Management
UAT – Service Management
Deploy to Live- Development Technology
Phase 2 development and activities
Prioritise issues that have small development and business need
Business Requirements – Application Management / Service Management
Estimate work required – Software Development / Application Management / Service Management
Development by Development Team, includes an implementation plan
Create and document UAT TEST Scenarios - Service Management
Document a TEST Plan – Application Management / Service Management
UAT – Service Management
Deploy to Live- Development Technology
Resources Skills and Cost
- ISG Software Development team
- Project Services
- Development Technology - involvement will be required for implementing into EUGEX, IDM and if any performance issues included in Priority list
- Testing will be carried out as service activity by Production/Service Management.
- Application Management / Service Management costs via support (4 days to be allocated from KSR for UAT)
- ITI UNIX agreement if needed to be confirmed