Organisation

Work/Task Breakdown

We have been provided with a high level estimate from COM007.  During the Analysis phase we will detail this plan into a concise work/task breakdown.  Doing this will be crucial to the success of the project.

We will provide a full re-estimation of the project costs at the end of Analysis.

The Project Manager will provide twice weekly updates on our project to the stakeholders.

 

Resources Skills and Cost

From our COM007 Estimate of 66 days we have the following breakdown by team:

Project Services 20%

Development Technology 50%

Production Teams 20%

Software Development 10%

 

Project Info

Project
IDM Database Migration to Oracle 11G
Code
COM019
Programme
ISG - Communication (COM)
Project Manager
Colin Forrest
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
27-Apr-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Overall Priority
Normal
Category
Compliance