Project journal
| Title | Description | Author | Post date |
|---|---|---|---|
| Weekly Update 0/5/08/16 |
All, Please find the weekly status update. RAG Status: Amber Activity since last update:
Planned |
Iain Moore-McLaughlin | 11-Aug-2016 |
| Weekly Update 22/07/2016 |
RAG STATUS - Amber Activity since last update: • Risks discussed and assigned to relevant personnel. • Contact made with relevant desktop support personnel and discussions planned for on site support. • Telephony solution in progress and looking good for completion. Planned • Approval of telephony proposal detailing what can/cannot be done given existing technology and current systems. • Commencement of telephony solution configuration. |
Iain Moore-McLaughlin | 27-Jul-2016 |
| Weekly Update 29/07/2016 |
All,
Please find the weekly status update. RAG Status: Amber Activity since last update:
Planned
Key Risks |
Iain Moore-McLaughlin | 29-Jul-2016 |
| Weekly Update 15/07/2016 |
RAG STATUS - Amber Activity since last update: • Further planning meeting went ahead including college admin staff now all returned from leave. • Site with adequate space, kit and network points secured to house all involved staff if required. • Plan created but still requires some fine tuning. Planned • Creation of telephony proposal detailing what can/cannot be done given existing technology and current systems. |
Iain Moore-McLaughlin | 15-Jul-2016 |
| Weekly Update 07/07/2016 |
RAG STATUS - Green Activity So Far * Kick off meeting went ahead as planned on Tuesday. * Activity commenced to nail down where College Admissions are with activity required of them. * High level view of outputs established (e.g. potential kit requirements, call scripts, support reqs. processes etc.). * Activity commenced on a brief technical proposal taking Ian Sutherlands call flow diagram into consideration. |
Iain Moore-McLaughlin | 15-Jul-2016 |