Plan

Document Sign-off

NameRoleDate signed off
 Project Sponsor 
 Project Manager 
   
   
   

 

 

Overview

This project follows the outcome of the Service monitoring requirements and options appraisal (2013/14)   and recommendations of the "INF107 - Environment Monitoring System - Assessment" project (2014/15).  

 

Background

 

 

 

 

Priority and Funding

 

 

Impact and Dependencies

 

Work/Task Breakdown

 

Project packages and milestones

Excel version of above

Resources Skills and Cost

Background

The current VMware service is running vSphere 5 and ESXi 5.5 on the hypervisors. vSphere 6 has been available for some time and we need to upgrade to this new release. This will provide us with better facilities to manage the clusters and new processes to streamline management.

 

Scope

The project will upgrade the vCenter infrastructure with a new highly available vCenter running on updated Windows Server virtual machines with an updated SQL Server clustered database.

 

Work/Task Breakdown

 

 

Resources Skills and Cost

 

 

 

Priority and Funding

This is a secondment project between the Institute for Academic Development, and the Careers Service.  Time allocation is 0.3FTE for a 2 year period, from both units.  Additional funding may be required for technical support.

 

Impact and Dependencies

 

 

Background

  Supporting PGT transitions

Taught Postgraduates often report their studies as a very intensive time, and the expectations on these students are very high – both academically, and in terms of why they are studying, and their future career plans. 

 

User Stories are logged & managed securely in Jira https://www.jira.is.ed.ac.uk/secure/RapidBoard.jspa?rapidView=321&view=planning.nodetail (N.B. EASE authentication required to access this link)