Impact and Dependencies

Background

 

Architecture DataCenter consists of eight VMware ESX hosts. Next year these will be reaching end of life. In order to save replacement costs it is planned to move the Virtual Machines into the IS Hosting Datacenter.

 

Scope

 

Migrate virtual machines onto IS Virtual Hosting Infrastructure

 

Objectives

 

Migrate all live VMs

To close down and retire eight ESX hosts

Free up VMware and Windows licences

 

Deliverables

 

All VM's migrated.

 

 

 