18/06/15 May Programme Meeting

 

 Decisions

ProjectDiscussion pointOutcome
HRS077 Improved reportingDecision needed on whether to push BI reports to live next week to take advantage of skilled resource availability in Apps ManagementAgreed that BI can go live next week
PPP001 Automate mat/patDecision needed on whether to do joint business analysis with Athena Swann requirements for College of Science & Engineering (CSE). CSE are willing to transfer days to cover the additional work.Agreed to joint analysis
PPP002 Online payslipsDecision need on whether to re-write PAY29 or just to address existing issues (Jiras)Agreed that PAY29 not to be re-written as part of this project.
PPP003 Annual MaintananceNeed agreement on whether additional security patch should be done as part of project or passed to support.Agreed to pass to support

Actions

ProjectActionActioned to
PPP003 Annual MaintananceCheck with Apps Management whether the additional patch can be done as part of normal supportAnne Mathison