Decisions
| Project | Discussion point | Outcome |
| HRS077 Improved reporting | Decision needed on whether to push BI reports to live next week to take advantage of skilled resource availability in Apps Management | Agreed that BI can go live next week |
| PPP001 Automate mat/pat | Decision needed on whether to do joint business analysis with Athena Swann requirements for College of Science & Engineering (CSE). CSE are willing to transfer days to cover the additional work. | Agreed to joint analysis |
| PPP002 Online payslips | Decision need on whether to re-write PAY29 or just to address existing issues (Jiras) | Agreed that PAY29 not to be re-written as part of this project. |
| PPP003 Annual Maintanance | Need agreement on whether additional security patch should be done as part of project or passed to support. | Agreed to pass to support |
Actions
| Project | Action | Actioned to |
| PPP003 Annual Maintanance | Check with Apps Management whether the additional patch can be done as part of normal support | Anne Mathison |