IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started Section Three: Projects In Progress Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
All projects for 16/17 have now started.
The programme status is set as AMBER as our priority project INF121 has significant overspend on first phase and high estimates for second phase. Other projects all good.




Section Two: Projects Not Started
Project Info |
Programme Manager's Commentary |
|
all projects started |
|
|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
INF119 (AP56-047)
Service Resilience Capability
Category: Discretionary
Milestones
RAG Status / RAG change during last month
GREEN
|
Report by Karen Stirling for March 2017
Achievements in Last Period
- Agreement gained to de-scope SRM activity from the project
- Dev Tech resource aligned to project activities for WIKI database failover
- Confirmed no work required on IDM Wiki connector
- Changes to IDM MyEd connector ready to deploy to test, waiting for update of IDM MyEd connector being completed on WEB009 project before completing change
- Agreed date for Dev database failover 10/11th April and week commencing 17th for Test
Issues
Next Steps
RAG Commentary
n/a
|
INF121
Migrate Core Databases to Oracle 12c
Category: Compliance
Milestones
RAG Status / RAG change during last month
RED
|
Report by Chris Konczak for March 2017
Achievements in Last Period
- GEN environment build is continuing
- UAT on NEWS from business users has been achieved
- Deployment of NEWS to LIVE has been achieved with no issues reported. Downtime was longer than anticipated due to the size and resulting time to copy over the databases.
Issues and Risks
- Budget is RED as costs are now 273 days total. NEWS took 126d, GEN is estimated as 55 days and APPS for 17/18 is estimated as 90 days
Next Steps
- Continue with GEN environment build
- Begin DEV, TEST and LIVE Pre migration testing
- Review of project plans and estimates for 16/17 and 17/18 will be carried out in April.
RAG Commentary
- Issue. Budget requires increased due to time taken to migrate NEWS. Meeting to review plans and estimates for 16/17, 17/18 will take place in April
|
INF122
16 - 17 Infrastructure Rationalisation
Category: Compliance
Milestones
RAG Status / RAG change during last month
GREEN
|
Report by David Watters for March 2017
Achievements in Last Period
- Wiki pages updated with latest information on remaining servers
- Business partners with outstanding queries contacted again
Issues and Risks
Next Steps
RAG Commentary
n/a
|
INF123
16-17 Provisioning of Python environment
Compliance
Milestones
RAG Status
Green
|
Report by Chris Orrell for March 2017
Achievements in Last Period
- In line with the project plan there was little to progress this period.
Issues
- The Python packaging repository work being carried out by INF124 is progressing. This needs to be completed and work co-ordinated with API126 project in order to demonstrate and release the Edgel Innovation work from Iteration.
- Containerisation continues to be an issue. The Product Owner is to prepare a containerisation strategy and roadmap for review and discussion.
Next Steps
- Plan the work necessary in order to release iteration 1.
- Monitor the outcome of the containerisation strategy and roadmap discussions.
- Iteration 2 is not due to start until the 1st of May and so the main project will now effectively pause until shortly before this time.
- A key stakeholder meeting has been scheduled for 24 April 'start-up' again.
-
RAG Commentary
The approach for containerisation is still to be confirmed.
RAG Commentary
- The project status is GREEN
RAG Commentary
n/a
|
INF124
Bamboo Upgrade 2016
Milestones
RAG Status
GREEN
|
Report by Gillian Henderson for March 2016
Achievements in Last Period
- Test Nexus Environment Built
- Test Nexus Environment Tested
- Test Nexus Environment Signed Off
- Test Bamboo Environment Built
- Test Bamboo Environment Tested
- Test Bamboo Environment Signed Off
- Live Nexus Environment Built
- Live Nexus Environment Tested
- Live Nexus Environment Delivered
- Live Bamboo Environment Built
- Live Bamboo Environment Tested
- Live Bamboo Environment Delivered
Issues and Risks
Next Steps
Complete Bamboo Environment tasks for Deployment Sign off
- Final TAD updates to be made including new diagram showing outgoing connections through Nexus and firewall change to block outgoing connections.
- Updated TAD circulated to Stakeholders and ITI.
- Deployment Checklist to be completed (Tech Man to confirm if require additional handover)
- CMDB to be updated with new server names.
- Agree date to decommission old Bamboo Servers. Production to raise call with ITI to remove on agreed date (Current servers powered down and unavailable but may be required for reference over coming months)
Complete Nexus Environment tasks for Deployment Sign off
- Final TAD updates to be made following feedback.
- Updated TAD circulated to Stakeholders and ITI for sign off.
- Deployment Checklist to be completed Tech Man (Tech Man to confirm if require additional handover.
- CMDB entry to be added for Nexus Service.
- Agree date to decommission old Nexus Environment. In meantime agree when can shut this server down. Production to raise call with ITI to remove on agreed date.
- Determine if tasks to update all plans to reference new Nexus URL is part of INF124 (if easy global update with 1-2 days effort) or if plans would be updated out with this INF124 on a project by project basis. – confirmation required by Stefan/Bill/Iain
|
INF125
System Monitoring Pilot 2
Discretionary
Milestones
RAG Status
GREEN
|
Report by Maurice Franceschi for March 2016
Achievements in Last Period
- project brief and planning - approved
- begin gathering requirements - started
Issues and Risks
Next Steps
- complete requirements gathering
Dates for pilot and subsequent set by WIS.
RAG Commentary
n/a
|
Section Four: Closed or Withdrawn Projects
Project Info |
Project Managers Commentary |
INF115 Python Development Platform Implementation |
Closure Approved August 2016 |
INF113 (AP45-067)
System Monitoring Pilot
|
Closure Approved 16 September 2016 |
INF111 (AP56-006)
New SQL Server Database Tier Replacement
|
Closure Approved 30 September 2016 |
INF118
JIRA upagrade 2016
|
Closure Approved 30 September 2016 |
INF120
Disaster Recovery for Priority Services
|
Closure Approved 3 March 2017 |
INF116
ASTA Upgrade 2016
|
Closure Approved 3 March 2017 |