July 2016
- Report Date
- July 2016
IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
A number of the remaining projects now have slipped into July or have been re-estimated and re-planned into 2016/17, resulting in unplanned carry over of circa 40 days. We anticpate being able to accomodate this from next year's budget.
Programme Owne and Programme Manager will meet before the new year begins to review current framework of accountability and responsibility to see how we can assist project teams in providing more realistic assessments of project status, project plans and risk management.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||
New SQL Server Database Tier Replacement Category: Compliance
Milestones
RAG Status/ RAG change during last month Project status is GREEN | Report by Karen Stirling for July 2016
Achievements in Last Period
Issues
Next Steps
The project current status is GREEN
| ||||||||||||||||||||||
System Monitoring Pilot Category: Discretionary
Milestones
RAG Status / RAG change during last month GREEN | Report by Colin Watt for for July 2016
Achievements in Last Period
Issues
Next Steps
The project current status is GREEN | ||||||||||||||||||||||
INF115 Python Development Platform Implementation D Milestones
RAG Status GREEN
| Report by Adam Wadee for July 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||
INF116 ASTA Upgrade 15/16 C Milestones
RAG Status GREEN | Report by Nikki Stuart for July 2016
Achievements:
Issues:
Next Steps:
Status Project status has been set to GREEN as the project is currently progressing to plan.
| ||||||||||||||||||||||
JIRA Upgrade 2016 Category: Compliance
Milestones
RAG Status / RAG change during last month GREEN
| Report by Chris Konczak for July 2016
Achievements in Last Period
Issues
Next Steps
The project current status is GREEN. | ||||||||||||||||||||||
Service Resilience Capability Category: Discretionary
Milestones
RAG Status / RAG change during last month GREEN | Report by Karen Stirling for July 2016
Achievements in Last Period
Issues
Next Steps
The project status is GREEN | ||||||||||||||||||||||
Disaster Recovery for Priority Services Category: Discretionary
Milestones
RAG Status / RAG change during last month GREEN | Report by Karen Stirling for July 2016
Achievements in Last Period
Issues
Next Steps
The project status is GREEN | ||||||||||||||||||||||
Migrate Core Databases to Oracle 12c Category: Compliance
Milestones
RAG Status / RAG change during last month RED | Report by Chris Konczak for July 2016
Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Automated Server Builds | Closure approved September 2015. |
Build and Configure new ColdFusion Version [15/16] | Closure approved December 2015 |
Closure approved December 2015 | |
INF117 (AP56-005) Bamboo Upgrade | Closure approved June 2016 |
INF105 (AP45-053) Decommission Obsolete Infrastructure | Closure approved July 2016 |
Install Oracle 12c | Closure approved July 2016 |