Report for March 2013

Report Date
March 2013

 

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

FIN080 - AMBER - Milestones need to be replanned due to slow progress and annual leave conflicts

FIN076 - RED - Issues identified during testing requiring supplier input. Integration testing to be rerun and UAT to be replanned

FIN085 - AMBER - Project Brief yet to be signed off and milestone missed. It is anticipated that sign off will be agreed on 3rd April and the delay accomodated within the current milestones

FIN079 - SUSPENDED - to restart in April

 

 

 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-059

eExpenses- Business Case

 

Compliance

 

Planning March 2013

Delivery August 2013

RAG Status

GREEN  

Plan

The project is due to start in Spring 2013, following the eFinancials Upgrade.

 

Dependencies

The project has no dependencies on other activity, however it is dependent on resource availability within Finance, so has been scheduled following the eFinancials Upgrade.

AP23-056

International Bank Validation

 

Funded 

Planning April 2013

Delivery December 2013

RAG Status

GREEN  

Plan

The project is due to start in April 2013. 

 

Dependencies

AP89-008

FPM for eInvoicing

 

Discretionary

Planning tbc

Delivery tbc

RAG Status

GREEN 

Plan

 This project has been delayed to 13/14 following the Mid Year Review.

 

Dependencies

 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

 

Category: Funded

Milestones

---

---

--- 

RAG Status

SUSPENDED

 

Report by Rhian Davies for October 2012

Project suspended

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

 

Category: Discretionary

Milestones

 

11-Apr-2013Integration
11-Apr-2013Acceptance
17-Apr-2013Deployment
01-May-2013Deployment review
15-May-2013Closure

RAG Status

RED

Report by Susan McKeown for March 2013

Achievements in Last Period  

  • Build stage was signed-off
  • The application was promoted to TEST
  • Integration testing was started

Issues

  • It transpired, when Integration testing commenced, that the payment pathway being used was not a specific test Finance Channel pathway which this project had mistakely believed had been supplied in November 2012. This issue is now with the Proejct Sponsor to resolve with the third party supplier. Integration testing and therefore UAT have now been postponed and will not be rescheduled until April 8. The project's RAG is RED due to this issue.

Next steps

  • Obtain test finance channel pathway from supplier
  • Agree go live date and delivery of live finance channel pathway with supplier
  • Complete Integration testing and re-work
  • Complete UAT
  • Complete comms to users
  • Deliver

 

 

 

 

 

 

 

FIN078 (AP Number)

eFin Journal Auto-Upload

 

Category: Discretionary

Milestones

 

Target dateTitle
08-Apr-2013Re-point to new eFin
24-Apr-2013Integration
03-Jun-2013Acceptance
11-Jun-2013Go-live
19-Jun-2013Deployment sign-off
27-Jun-2013Closure

RAG Status

GREEN

Report by Dawn Nicholls for March 2013

Achievements this period

  • The Dev application passed peer testing and the build stage was signed-off on 5th March

Issues

  • The project was made aware that the new eFIn database was located on a new server, so additional work/complexity was encountered in repointing the Dev application which has delayed the progression to Test.  New milestone dates have now been set.

Next steps

  • Deploy to Test for integration/acceptance testing

 

  Full details can be seen in the Project Journal

FIN079 (AP Number)

LEAN- Review of Financial Systems

 

Category: Discretionary

Milestones

 

Target dateTitle
31-May-2013Delivery - workpackage 5
31-May-2013Delivery - workpackage 2
31-May-2013Delivery - workpackage 4
31-May-2013Delivery - workpackage 3
14-Jun-2013Closure

RAG Status

BLUE (suspended until April)

Report by Dawn Nicholls for March 2013

Achievements this period

  • N/A as project suspended until April to allow for eFIn upgrade project to progress unhindered

Issues

  • N/A

Next steps

  • Meeting scheduled with FInance for w/c 01/04/13 to re-activate the project

 

Full details can be seen in the Project Journal

FIN080 (AP Number)

Customer Interface Improvements

 

Category: Discretionary

Milestones

 

Target dateTitle
01-Mar-2013Phase 2 - Design
24-May-2013Phase 2 - Build
28-Jun-2013Phase 2 - Integration
12-Jul-2013Phase 2 - Acceptance
19-Jul-2013Phase 2 - Go-live
26-Jul-2013Phase 2 - Deployment
12-Aug-2013Closure

RAG Status

AMBER

Report by Dawn Nicholls for March 2013

Achievements this period

  • Meetings with Finance to clarify requirements for phase 2
  • Internal IS meetings to agree best soaftware architecture to support the business requirements

Issues

  • Slow progress with phase 2 design
  • Lack of clarity on business requirements for historical feed
  • Annual leave has hindered progress

Next steps

  • Agree priorities for phase 2
  • Replan milestone dates
  • Sign-off design for phase 2

 

 Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

 

Category: Discretionary

Milestones

---

---

--- 

RAG Status

SUSPENDED

Report by Rhian Davies for October 2012

Project suspended

FIN083  (AP23-003)

eFinancials Upgrade

 

Category: Compliance

Milestones

 

 

  
27-Mar-2013Deployment Sign Off
10-Apr-2013Closure

 

RAG Status

GREEN

 

Report by Morna Findlay for Rhian Davies for March  2013

Achievements in this period
  1. Estates  interfaces signed off in  TEST and deployed to LIVE

  2. Salary forecasting issues resolved

  3. POPR50 issue resolved

  4. PECOS interface  issues resolved

  5. Old EFIN DEV and TEST databases and applications taken down.

  6. 63 JIRA issues resolved.

  7. Script killing orphaned processes now runs nightly.

 

Outstanding Issues
  1. 52 JIRA issues remaining.

  2. Batch processing issue - awaiting ABS fix for CLIR09

  3. Issues with Spinning processes - possible  ACTRB9 FIX to be deployed to LIVE

  4. New version of Supplier Self-Service supplied by ABS to be deployed to DEV and TEST and tested.

  5. Issues with new PCs accessing EFIN - workaround in place, ABS fix awaited

  6. Sciquest extract issue resolution - to be tested and confirmed

  7. Deployment Sign-Off review missed.

 

Next Steps
  1. Remaining issues to be resolved - Finance and IS Apps staff to update JIRA issues

  2. Deployment of Supplier Self-Service Portal - new version supplied by ABS to resolve performance issues.

  3. Lessons learned to be captured

  4. Documentation to be completed

  5. Deployment sign-off review.

 

The project RAG status has been set to AMBER as a new date for the Deployment Sign-Off review has yet to be agreed and the closure date of April 10th will not be achievable.

 

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

 

15-Mar-2013Project Brief signed off
29-Mar-2013Prioritised list of requirements agreed
15-May-2013System Design signed off
27-Sep-2013UAT (for final release) signed off
25-Oct-2013Deployment signed off
15-Nov-2013Closure

 

 

RAG Status:  AMBER (due to delayed sign-off for Brief)

Report by Jill Nicoll for March 2013

Achievements in last period:

Project Brief approved by the Programme Manager, and submitted to Project Sponsor for review and comment.

IS Applications project resources secured.

Business Analysis completed and the top eight build priorities assigned. 

Issues:

The Brief has not yet been approved by the Project Sponsor.

Final updates to the Business Requirements Document were agreed in the meeting of 27th March, but the revised document has not yet been formally signed off by the Stakeholder group.  This sign-off is expected to be confirmed in the meeting of 3rd April.

Next Steps:

Project Brief to be reviewed by Project Sponsor, and signed off.

Business Analysis stage sign-off to be confirmed by stakeholder group.

System Design will progress throughout April.

 

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for March 2013

 

Achievements in last period:

  • Project manager assigned 

 

Issues

  • None

 

Next Steps

  • Kick off meeting with Finance
  • Complete Planning phase

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

 

Milestones

 

Target dateTitle
05-Apr-2013Project Brief

 

 

 

RAG Status:  GREEN

Report by Laura Bell for March 2013

 

Achievements in last period:

  • Project Initiated

  • Initial scoping/ requirements gathering underway

  • Project Brief prepared

 

Issues

  • None

 

Next Steps

  • Sign off Project BriefComplete Planning phase

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

Report by Louise Heathcote for March 2013

 

Achievements in last period:

  • Project Initiated

  • Initial scoping/ requirements gathering underway

  • Project Brief prepared

 

Issues

  • None

 

Next Steps

  • Sign off Project BriefComplete Planning phase

 

Section Four: Closed or Withdrawn Projects

 

 

 

 

 

 

Project InfoProject Managers Commentary

FIN082

HMRC Real Time Information

Compliance 

Report by Jill Nicol

This project was closed on 10-Aug-2010

Please see the Completion Report for further information.  

AP23-055

Rolling out Finance BOXI Reports

 

Funded 

Report by Rhian Davies

This project was withdrawn from the 12/13 programme.

FIN072 (AP01-008)

eTime

 

Category: Compliance

Report by Jill Nicol

This project was closed on 30-Nov-12.

Please see the Completion Report for further information.

FIN077

Control Account Balancing

 

Category: /Compliance

Report by Sue Woodger 

This project was closed 1 February 2013

Please see the Completion Report

FIN084

eStores Rollout

Category : Discretionary

 

Report by Dawn Nicholls

This project was closed on 20th December 2012

Please see the Completion Report for further information