Report for September 2019

Report Date
September 2019

Resource Position

 

 

Forward Look

 

 

 

 

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

N/A

N/A

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN119 (AP67-024)

eInvoicing

Core Funded

 

Milestones:

Agreed at WIS - 30-Jul-2019, these need to be confirmed with Finance against the latest Project Proposal:

Milestone Due Date
Development & Deployment of the API / XML Handler 07-Aug-2019
Start Pilot, On-board the First Supplier (XMA Ltd) 26-Aug-2019
On-board Next 2 Suppliers (Fisher Scientific UK Ltd and Blackwell UK Ltd) to Pilot 16-Sep-2019
Agree Sign Off of / Closure of Pilot - eInvoicing Now LIVE 30-Sep-2019
Deployment / eInvoicing Sign Off 11-Oct-2019
Project closure 18-Oct-2019

 

RAG Status : AMBER

 

Report By Richard Bailey for September 2019

 

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • Works have continued against the draft proposal to complete the project, though still to be formally agreed with Finance, but good progress has been made
  • The LIVE pilot has been expanded, with Suppliers Fisher Scientific UK Ltd and Blackwell UK Ltd added to the first Supplier (XMA Ltd).  The pilot continues to work as expected and has now handled in excess of 300 invoices in three weeks.
  • Emma McNab is taking over the Project from Richard Bailey

Issues

 

Next Steps

  • Look to achieve sign off  from Finance against the latest Project Proposal
  • PICCL the change / agree revised budget sign off of the proposal once agreed 
  • Complete the eInvoicing Pilot and maintenance period 
  • Draft a Closure Report
  • Agree Project Sign Off / Closure

 

FIN126

Core Funded

Essential Finance System Compliance Updates and Document Revitalisation

 

Milestones:

Proposed milestones are:

Stage Milestone Due Date Complete   
Plan

 (A) Signed Letter of engagement

20-March-2019  Yes
Plan  Planning Complete (Project Brief) 03-May-2019  Yes
Analyse     (B) Business Analysis Complete          07-June-2019  Yes
Execute  (A) Completion of For:sight Proof of Concept phase 27-Sept-2019  No
Analyse  Re-Planning Post Compliance (Phase (B)) Scoping 19-July-2019  Yes
Build  (B) Build Complete 13-Sept-2019  Yes
Accept  (B) Acceptance Testing Complete 27-Sept-2019  Yes
Deliver  (A) Purchase of Arkk, For:sight bridging software 25-Oct-2019  No
Deliver  (B) Deploy to Live 18-Oct-2019  No
Close  Project Closure 31-Oct-2019  No

 

RAG Status: AMBER

Report By Ken Miller for September 2019

Achievements in Last Period:

Work Stream (A)

  • Configuration issues between For:sight and Finance required inputs remain outstanding but should be resolved by the middle on October.
  • Testing shows that the majority of required inputs can now be processed by Arkk For:sight and a VAT return generated.
  • The Tax Office have escalated the outstanding issues with Arkk with the hope for quick resolution.

Work Stream (B)

  • Finance continued to liaise with Advanced in response to outstanding issues.  Advanced consultant providing remote support to resolve issues.
  • UAT undertaken via TestRail.  UAT finally signed off on 10/9/2019.
  • As "Change Freeze" was in effect Emergency CAB raised to allow updates to be promoted to live on 16/9/2019.
  • Updates were released to live on 16/9.  Initial tests suggested that the upgrade was successful but later testing highlighted that this was not the case with installment plan letters and reminders not being correct.
  • Finance liaised with Advance until resolution of core reminders problem was resolved on 25/9. 

Issues:

  • (A) It has been confirmed that we will require a new legal contact.  Joanne MacConnell will be replaced by Esther Duncan.  Joanne's last day is 4th Oct and Esther doesn't start until November so there will be a gap.  During this period any correspondence should go to legalservices@ed.ac.uk, and a colleague will pick this up.
  • (A) There remains a small manual element to the MTD process which may make it non MTD compliant.  This risk has raised with the UoE Tax Office and they have agreed that they are the owner of this risk.
  • (B) The release to Live did not progress as smoothly as had been expected with a couple of issues still outstanding.  A review meeting has been arranged to identify the issues to ensure lesson's are learnt. 

Next Steps:

Work Stream (A)

  • Dual run of VAT return via For:sight for last quarters VAT return to be carried out.  
  • Review meeting scheduled for Oct 23rd.  It is hoped that a mirror June VAT return via For:sight will have been possible prior to this meeting and a comparison of the generated VAT returns undertaken.
  • DPIA to be addressed once UAT has been signed off.
  • Clarify issues F Eardley has raised regarding the Arkk SLA.
  • Contact Arkk regarding the process to promote instance from PoC to Live.

Work Stream (B)

  • Liaise with Advanced regarding resolution of outstanding issues.
  • Schedule release of resolution files once they have been signed off.
  • Carry out review of post go live issues and record in lesson's learned log to ensure they do not happen again.

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date Complete  
Planning 01-Feb-2019  Yes
Analysis 03-May-2019  No
Solution Options 07-Jun-2019  No
Implementation Plan 28-Jun-2019  No
Delivery 30-Sep-2019  No
Closure 28-Oct-2019  No

 

RAG Status : AMBER

 

Report By Ken Miller for September 2019

Achievements in Last Period:

  • Analysis ongoing to confirm system owners and Finance responsibility with regards GDPR data compliance.

Issues

  • The revised number of systems that fall within the scope of the project means that once confirmed the project timescales will have to be re-estimated.
  • As a result of increased number of projects in scope it is proposed that projects identified to be replaced by the Core system will not be analysed with regards their GDPR requirements.
  • As a result of rebalancing workloads the PM for this project is to transition from Ken Miller to Emma McNab.

Next Steps

  • Confirm projects that should be in scope of project.

  • Revised project scope to be run past the Project Sponsor.

  • For systems not in scope but containing Finance data, contact system owners to confirm responsibility for GDPR compliance.

  • Re-planning meeting  required to review confirmed scope and to confirm revised schedule and tasks to be carried out under this project.

 

FIN128

FPM Upgrade

Core Funded

Milestones

Milestone Due Date
Acceptance Testing Complete       15-11-2019
Delivery Complete  25-11-2019
Project Closure  06-12-2019

 

 RAG Status : GREEN

 

Report By Kevin Hone for September 2019

Achievements in Last Period:

  • Change in budget was agreed with Finance and WIS. This unfortunately has seen an increase from 42 to 52 days.
  • Change in delivery date was agreed with Finance and WIS. This has led to a move from the 9th October to 25th November.

Issues:

  • Finance resource constraints and focus on higher prioritised project work means that User Acceptance Testing (UAT) has yet to be concluded.

Next Steps:

  • Preparations for implementation.

FIN133

Corporate Planner Upgrade

Core Funded

Milestones

Milestone Due Date
Build Complete 07-10-2019
UAT Complete 16-10-2019
Deployment Complete       17-10-2019
DSOR Sign-Off 25-10-2019
Project Closure 08-11-2019

 

 RAG Status : GREEN

Report By Kevin Hone for September 2019

Achievements in Last Period:

  • Project Brief Signed-off.
  • Project team and third party all engaged.
  • Work is progressing ahead of plan with early indications of achieving deployment on the 17th October rather than originally scheduled for the 15th November.

Issues:

  • None.

Next Steps:

  • Preparations for implementation.

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

 

Closure Report

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Closure Report

FIN125

Media Production for Annual Report and Accounts    

Closure Report

FIN129

PCI DSS 

Closure Report

 