FIN119 (AP67-024)
eInvoicing
Core Funded
Milestones:
Agreed at WIS - 30-Jul-2019, these need to be confirmed with Finance against the latest Project Proposal:
RAG Status : AMBER
|
Report By Richard Bailey for August 2019
For reference: SG = Scottish Government, SGS = Scottish Government Solution
Achievements this Period
- A draft proposal to complete the project, though still to be formally agreed with Finance, has seen the Project milestones reset and the Project status will reduced back to Amber
- Look to achieve sign off from Finance against the latest Project Proposal
- The eInvoicing application code has been successfully deployed to LIVE
- A LIVE pilot has been initiated with the first Supplier (XMA Ltd) - 28-Aug-2019 and invoices are being received and progressing through the eInvoicing dashboard as expected
Issues
Next Steps
- Look to achieve sign off from Finance against the latest Project Proposal
- PICCL the change / agree revised budget sign off of the proposal once agreed
- Continue the eInvoicing Pilot and look to add the Suppliers Fisher Scientific UK Ltd and Blackwell UK Ltd during September
|
FIN126
Core Funded
Essential Finance System Compliance Updates and Document Revitalisation
Milestones:
Proposed milestones are:
Stage |
Milestone |
Due Date |
Complete |
Plan |
(A) Signed Letter of engagement
|
20-March-2019 |
Yes |
Plan |
Planning Complete (Project Brief) |
03-May-2019 |
Yes |
Analyse |
(B) Business Analysis Complete |
07-June-2019 |
Yes |
Execute |
(A) Completion of For:sight Proof of Concept phase |
27-Sept-2019 |
No |
Analyse |
Re-Planning Post Compliance (Phase (B)) Scoping |
19-July-2019 |
Yes |
Build |
(B) Build Complete |
13-Sept-2019 |
No |
Accept |
(B) Acceptance Testing Complete |
27-Sept-2019 |
No |
Deliver |
(A) Purchase of Arkk, For:sight bridging software |
25-Oct-2019 |
No |
Deliver |
(B) Deploy to Live |
18-Oct-2019 |
No |
Close |
Project Closure |
31-Oct-2019 |
No |
RAG Status: GREEN
|
Report By Ken Miller for July 2019
Achievements in Last Period
Work Stream (A)
- Configuration issues between For:sight and Finance required inputs resolved.
- Initial testing shows that all required inputs can now be processed by Arkk For:sight and the VAT return generated.
Work Stream (B)
- UAT undertaken via TestRail. A number of issues raised regarding the work undertaken by Advanced consultant.
- In response to outstanding issues Advanced consultant on site with Finance on 14th to walk through and resolve outstanding issues.
- Although it was thought all issues had been resolved UAT by the business find a nuber of issues.
- Summary of outstanding issues being raised with Advanced for resolution.
Issues
- (A) It has been reported that we may require a new legal contact. This needs confirmed so that impact on the project can be minimised.
- (A) There remains a small manual element to the MTD process. Confirmation required from HMRC that this level of manual intervention is acceptable.
- (B) If any of the updates require to be rolled out prior to matriculation this will have to be via the emergency process as the ISG change freeze is now in place.
Next Steps
Work Stream (A)
- Dual run of VAT return via For:sight for last quarters VAT return to be carried out.
- Review meeting scheduled following comparison VAT return run to review the VAT process via For:sight and the range of discrepancy between old and new VAT responses.
- DPIA to be addressed once UAT has been signed off.
Work Stream (B)
- Completion review of post development issues.
- Liaise with Advanced regarding resolution of outstanding issues.
|
FIN127
Finance General Data Protection Regulation (GDPR)
Core Funded
Milestones
RAG Status : AMBER
|
Report By Ken Miller for July 2019
Achievements in Last Period
-
Following project review Data Protection Officer provided steer on the type of projects that should be the responsibility of Finance with regards GDPR compliance.
-
Analysis carried out to confirm system owners and Finance responsibility with regards GDPR data compliance.
- Review meeting held to identify revised scope of project.
Issues
- The revised number of systems that fall within the scope of the project means that once confirmed the project timescales will have to be re-estimated.
Next Steps
-
Confirm projects that should be in scope of project.
-
For systems not in scope but containing Finance data, contact system owners to confirm responsibility for GDPR compliance.
-
Re-planning meeting required to review confirmed scope and to confirm revised schedule and tasks to be carried out under this project.
|
FIN128
FPM Upgrade
Core Funded
Milestones
RAG Status : GREEN
|
Report By Kevin Hone for August 2019
Achievements in Last Period:
- Change in delivery date was agreed with Finance and WIS. This has led to a move from the 13th August to 9th October.
Issues:
- Finance resource constraints and focus on higher prioritised project work means that UAT has yet to be concluded.
Next Steps:
- Preparations for implementation
|
FIN129
PCI DSS Audit
Core Funded
Milestone |
Due Date |
Project Delivery |
30/08/19
|
Project Closure |
30/08/19
|
RAG Status : AMBER
|
Report By Kevin Hone for August 2019
Achievements in Last Period:
- Project closure report was issued.
- Finance and WIS approved a change request to move the project completion date to the end of August.
Issues:
- A recommendations paper has been drafted by Finance and issued for comment but as yet, not approved. This is the only action preventing project closure.
Next Steps:
- To allow time for review, revision and sign-off of the recommendations paper a target date of the 13th September has been agreed with the project sponsor.
|