Report for May 2019

Report Date
May 2019

Resource Position

 

Note: The current 18/19 Finance programme budget allocation (at 04-June-2019) for FIN128 (FPM Upgrade) is now 35 days.

 

Forward Look

 

 

 

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

N/A

N/A

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN119 (AP67-024)

eInvoicing

Core Funded

Agreed at WIS - 26-Apr-2019, these will need reviewing again in light of continued bug fixes / acceptance testing:

Target Date Title  
03-May-2019   Development & Deployment of the API / XML Handler  
28-May-2019 On-board the First 3 Suppliers  
25-Jun-2019 On-board the Second 5 Suppliers  
05-Jul-2019 Phase 2 – Deployment sign off  
12-Jul-2019 Project closure  

 

RAG Status : RED

 

Report By Richard Bailey for May 2019

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • The Project remains escalated to the Senior Supplier and Head of Development Services
  • Work packages / development of the API / XML Handler (all original 'Must Have' Jira) are complete but works continue on bugs after acceptance testing (please see Issues below)
  • Acceptance testing at an advanced stage, though not yet completed due to bugs
  • Resource and budget to complete any recognised / agreed show stopper Jira have been secured and FIN119 continues to work closely with MLE005  
  • Agree / firm up new milestones and agree a date to Go live, in coordination with the SG (28th May 2019 was touted)

 

Issues

 

Next Steps

  • Complete acceptance testing / finish work against bugs, working closely with MLE005 and the Resource Manager to maintain Developer access
  • Agree / firm up further revised milestones and agree another date to Go live, in coordination with the SG (11th June 2019 is now touted)
  • PICCL milestones once acceptance testing is completed / the dates are agreed 
  • Deploy / go live with the first Supplier (XMA Ltd) 
  • Agree date to on-board further Suppliers
  • Secure Developer Resource (in agreement with MLE005 / Resource Manager) to complete handover to Production

 

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Closure Review 31-Jul-2019

 

RAG Status: GREEN

Report By Tim Gray for May 2019

Achievements in Last Period

Issues

  • None

Next Steps

  • Film and complete post-production for SRS lecture
  • Confirm and plan future content production.

FIN126

Core Funded

Essential Finance System Compliance Updates and Document Revitalisation

 

Milestones:

Proposed milestones are:

Stage Milestone Due Date Complete   
Plan

 (A) Signed Letter of engagement

20-March-2019  Yes
Plan  Planning Complete (Project Brief) 03-May-2019  Yes
Analyse     (B) Business Analysis Complete          07-June-2019  No
Execute  (A) Completion of For:sight Proof of Concept phase 14-June-2019  No
Analyse  Re-Planning Post Compliance (Phase (B)) Scoping 14-June-2019  No
Build  (B) Build Complete 28-June-2019  No
Accept  (B) Acceptance Testing Complete 05-July-2019  No
Deliver  (A) Purchase of Arkk, For:sight bridging software 19-July-2019  No
Deliver  (B) Deploy to Live 19-July-2019  No
Close  Project Closure 02-Aug-2019  No

 

RAG Status: GREEN

Report By Ken Miller for May 2019

 

Achievements in Last Period

  • Project brief sign off.
  • Kick off work stream (B) with IS BA to initiate requirements capture and analysis.
  • Meetings held with Finance to confirm present position regarding both project work streams. 
  • On-going work between Finance and Arkk to complete PoC environment.
  • Finance have been carrying out testing as the POC environment is developed.

Issues

  • It has been reported that we may require a new legal contact.  This needs confirmed so that impact on the project can be minimised.

Next Steps

Work Stream (A)

  • Completed POC instance expected to be finalised by 7/6/2019.
  • UAT undertaken.
  • Dual run of For:sight output against present process to be undertaken for the last quarter.
  • DPIA requirements raised with the Data Protection Officer (DPO).

Work Stream (B)

  • Completion of initial requirements capture.
  • Review of requirements and prioritisation of work to be carried out. 

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date Complete  
Planning 01-Feb-2019  Yes
Analysis 03-May-2019  No
Solution Options 07-Jun-2019  No
Implementation Plan 28-Jun-2019  No
Delivery 30-Sep-2019  No
Closure 28-Oct-2019  No

 

RAG Status : AMBER

 

Report By Ken Miller for May 2019

 

Achievements in Last Period

  • Review of Finance artefacts almost complete with regards identification of GDPR data.
  • BA resource from IS Applications initiated GDPR compliance project analysis phase.
  • Internal review of 2018/19 timescales to free contingency for use by FIN119

Issues

  • Key Finance resource, John Bannaghan, to be seconded to the Core project at the end of May.  Resource has been identified to backfill this position.

Next Steps

  • Confirm scope of implementation of GDPR patch.

  • Completion of GDPR compliance analysis phase.

  • Re-planning of scope of 2018/19 work based upon GDPR compliance analysis results.

  • Internal review of 2018/19 timescales to free contingency.

 

FIN128

FPM Upgrade

Core Funded

Milestones

Milestone Due Date
Planning 01-03-2019
Delivery 22-07-2019
Closure 01-08-2019

 

 RAG Status : AMBER

Report By Leon Toland for May 2019

Achievements in Last Period:

  • Release and deployment of FPM v2.4.0.17 in Dev
  • Initial Finance-team UAT testing activities in Dev environment

Issues:

  • Potential availability of sufficient Finance UAT resources to support FPM acceptance testing (in Test), whilst FIN119 is the FIN programme priority in 18/19

Next Steps:

  • Deployment of FPM v2.4.0.17 in Test environment
  • Dev Technology team assessment of resolution level of FPM penetration testing issues (found during FIN118) in Dev environment.
  • Finance-team UAT testing activities in Test environment

 

FIN129 - PCI DSS Audit

Core Funded

 Project Initiation Complete 22/04/19
 Project Planning Complete 07/06/19
 Workshop 1 - Scope Complete 27/05/19

 Workshop 2 - Actions Complete

12/06/19

 Workshop 3 - Options Complete

27/06/19

 Workshop 4 - Recommendations   

10/07/19
Project Delivery Sign-off

26/07/19

Project DSOR Sign-off

02/08/19

 

 RAG Status : GREEN

Report By Kevin Hone for May 2019

Achievements in Last Period:

  • A workshop between business (Finance) and technology took place towards the end of the month with a focus on identification of key stakeholders and consensus on project scope.
  • A commitment has been made to attend workshops with future placeholder dates added to people’s diaries.

Issues:

  • There is an on-going debate as to what should/shouldn’t be in scope amongst technology resource.
  • A pragmatic approach and agreement on scope will be required to achieve a timely sign-off of the project brief.
  • There is on-going limited availability of technical resource to support discussions on the project.

Next Steps:

  •  A meeting with Finance is to be scheduled to determine what might be progressed outside of future workshops.
  •  A workshop to review open actions:
    • An updated list of known VOIP users.
    • A shortened list of specific questions that cannot be completed by the internal assessor.
    • Supplementary wording to support the system diagram (since shared as web-site links).

 

 

 

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

 

Closure Report

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Closure Report