Project Info
|
Project Managers Commentary
|
FIN119 (AP67-024)
eInvoicing
Core Funded
Agreed at WIS - 26-Apr-2019, these will need reviewing again in light of continued bug fixes / acceptance testing:
RAG Status : RED
|
Report By Richard Bailey for May 2019
For reference: SG = Scottish Government, SGS = Scottish Government Solution
Achievements this Period
- The Project remains escalated to the Senior Supplier and Head of Development Services
- Work packages / development of the API / XML Handler (all original 'Must Have' Jira) are complete but works continue on bugs after acceptance testing (please see Issues below)
- Acceptance testing at an advanced stage, though not yet completed due to bugs
- Resource and budget to complete any recognised / agreed show stopper Jira have been secured and FIN119 continues to work closely with MLE005
- Agree / firm up new milestones and agree a date to Go live, in coordination with the SG (28th May 2019 was touted)
Issues
Next Steps
- Complete acceptance testing / finish work against bugs, working closely with MLE005 and the Resource Manager to maintain Developer access
- Agree / firm up further revised milestones and agree another date to Go live, in coordination with the SG (11th June 2019 is now touted)
- PICCL milestones once acceptance testing is completed / the dates are agreed
- Deploy / go live with the first Supplier (XMA Ltd)
- Agree date to on-board further Suppliers
- Secure Developer Resource (in agreement with MLE005 / Resource Manager) to complete handover to Production
|
FIN125
Media Production for Annual Report and Accounts
Sponsor Funded
Milestones
RAG Status: GREEN
|
Report By Tim Gray for May 2019
Achievements in Last Period
- Staff welcome with Peter Mathieson filmed and post-production completed
- Pre-production for SRS lecture completed
Issues
Next Steps
- Film and complete post-production for SRS lecture
- Confirm and plan future content production.
|
FIN126
Core Funded
Essential Finance System Compliance Updates and Document Revitalisation
Milestones:
Proposed milestones are:
Stage |
Milestone |
Due Date |
Complete |
Plan |
(A) Signed Letter of engagement
|
20-March-2019 |
Yes |
Plan |
Planning Complete (Project Brief) |
03-May-2019 |
Yes |
Analyse |
(B) Business Analysis Complete |
07-June-2019 |
No |
Execute |
(A) Completion of For:sight Proof of Concept phase |
14-June-2019 |
No |
Analyse |
Re-Planning Post Compliance (Phase (B)) Scoping |
14-June-2019 |
No |
Build |
(B) Build Complete |
28-June-2019 |
No |
Accept |
(B) Acceptance Testing Complete |
05-July-2019 |
No |
Deliver |
(A) Purchase of Arkk, For:sight bridging software |
19-July-2019 |
No |
Deliver |
(B) Deploy to Live |
19-July-2019 |
No |
Close |
Project Closure |
02-Aug-2019 |
No |
RAG Status: GREEN
|
Report By Ken Miller for May 2019
Achievements in Last Period
- Project brief sign off.
- Kick off work stream (B) with IS BA to initiate requirements capture and analysis.
- Meetings held with Finance to confirm present position regarding both project work streams.
- On-going work between Finance and Arkk to complete PoC environment.
- Finance have been carrying out testing as the POC environment is developed.
Issues
- It has been reported that we may require a new legal contact. This needs confirmed so that impact on the project can be minimised.
Next Steps
Work Stream (A)
- Completed POC instance expected to be finalised by 7/6/2019.
- UAT undertaken.
- Dual run of For:sight output against present process to be undertaken for the last quarter.
- DPIA requirements raised with the Data Protection Officer (DPO).
Work Stream (B)
- Completion of initial requirements capture.
- Review of requirements and prioritisation of work to be carried out.
|
FIN127
Finance General Data Protection Regulation (GDPR)
Core Funded
Milestones
RAG Status : AMBER
|
Report By Ken Miller for May 2019
Achievements in Last Period
- Review of Finance artefacts almost complete with regards identification of GDPR data.
- BA resource from IS Applications initiated GDPR compliance project analysis phase.
- Internal review of 2018/19 timescales to free contingency for use by FIN119
Issues
- Key Finance resource, John Bannaghan, to be seconded to the Core project at the end of May. Resource has been identified to backfill this position.
Next Steps
-
Confirm scope of implementation of GDPR patch.
-
Completion of GDPR compliance analysis phase.
-
Re-planning of scope of 2018/19 work based upon GDPR compliance analysis results.
-
Internal review of 2018/19 timescales to free contingency.
|
FIN128
FPM Upgrade
Core Funded
Milestones
RAG Status : AMBER
|
Report By Leon Toland for May 2019
Achievements in Last Period:
- Release and deployment of FPM v2.4.0.17 in Dev
- Initial Finance-team UAT testing activities in Dev environment
Issues:
- Potential availability of sufficient Finance UAT resources to support FPM acceptance testing (in Test), whilst FIN119 is the FIN programme priority in 18/19
Next Steps:
- Deployment of FPM v2.4.0.17 in Test environment
- Dev Technology team assessment of resolution level of FPM penetration testing issues (found during FIN118) in Dev environment.
- Finance-team UAT testing activities in Test environment
|
FIN129 - PCI DSS Audit
Core Funded
Project Initiation Complete |
22/04/19 |
Project Planning Complete |
07/06/19 |
Workshop 1 - Scope Complete |
27/05/19 |
Workshop 2 - Actions Complete
|
12/06/19
|
Workshop 3 - Options Complete
|
27/06/19
|
Workshop 4 - Recommendations
|
10/07/19 |
Project Delivery Sign-off |
26/07/19
|
Project DSOR Sign-off |
02/08/19
|
RAG Status : GREEN
|
Report By Kevin Hone for May 2019
Achievements in Last Period:
- A workshop between business (Finance) and technology took place towards the end of the month with a focus on identification of key stakeholders and consensus on project scope.
- A commitment has been made to attend workshops with future placeholder dates added to people’s diaries.
Issues:
- There is an on-going debate as to what should/shouldn’t be in scope amongst technology resource.
- A pragmatic approach and agreement on scope will be required to achieve a timely sign-off of the project brief.
- There is on-going limited availability of technical resource to support discussions on the project.
Next Steps:
- A meeting with Finance is to be scheduled to determine what might be progressed outside of future workshops.
- A workshop to review open actions:
- An updated list of known VOIP users.
- A shortened list of specific questions that cannot be completed by the internal assessor.
- Supplementary wording to support the system diagram (since shared as web-site links).
|