AP12-017

Decommissioning of ERA

 

Compliance

 

Planning March 2013

Delivery October 2013

RAG Status

GREEN  

Plan

 The project is scheduled to start in March 2013, following the eFinancials Upgrade.

 

Dependencies

This project cannot start until all activity involving ERA is transferred to an alternative solution.

AP23-059

eExpenses- Business Case

 

Compliance

 

Planning March 2013

Delivery August 2013

RAG Status

GREEN  

Plan

The project is due to start in March 2013, following the eFinancials Upgrade.

 

Dependencies

The project has no dependencies on other activity, however it is dependent on resource availability within Finance, so has been scheduled following the eFinancials Upgrade.

AP23-056

International Bank Validation

 

Funded 

Planning April 2013

Delivery December 2013

RAG Status

GREEN  

Plan

The project is due to start in April 2013. 

 

Dependencies

AP89-008

FPM for eInvoicing

 

Discretionary

Planning tbc

Delivery tbc

RAG Status

GREEN 

Plan

 This project has been delayed to 13/14 following the Mid Year Review.

 

Dependencies

 

 

Section Three: Projects in Progress

 

 

 

 

 

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

 

Category: Funded

Milestones

---

---

--- 

RAG Status

SUSPENDED

 

Report by Rhian Davies for October 2012

Project suspended

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

 

Category: Discretionary

Milestones

 

08-Mar-2013Build
11-Apr-2013Integration
11-Apr-2013Acceptance
17-Apr-2013Deployment
01-May-2013Deployment review
15-May-2013Closure

RAG Status

GREEN (assuming revised budget approved at WIS 08/03/13)

 

Report by Susan McKeown for February 2013

Achievements in Last Period  

  • Build work was completed  with all issues in peer testing resolved and re-tested
  • The application was re-worked to use Central Auth rather than CCD

Issues

  • The project was delayed due to resource conflicts with FIN083 eFinancials upgrade
  • The budget needed increased to accommodate re-work from peer testing and 2 days for changing to Central Auth

Next steps

  • Build Review
  • Promote the application to TEST
  • Integration testing
  • UAT

 

 

 

 

 

 

 

FIN078 (AP Number)

eFin Journal Auto-Upload

 

Category: Discretionary

Milestones

 

Target dateTitle
13-Mar-2013Re-point to new eFin
02-Apr-2013Integration
09-May-2013Acceptance
17-May-2013Go-live
27-May-2013Deployment sign-off
11-Jun-2013Closure

RAG Status

GREEN

Report by Dawn Nicholls for February 2013

Achievements this period

  • Build work completed
  • Peer testing of build completed
  • Build milestone

Issues

  • Knock-on delays from peer testing, caused by impact of eFin upgrade and unavailability of Dev environment

Next steps

  • Complete move to new upgraded eFIn database
  • Integration testing

 

  Full details can be seen in the Project Journal

FIN079 (AP Number)

LEAN- Review of Financial Systems

 

Category: Discretionary

Milestones

 

Target dateTitle
31-May-2013Delivery - workpackage 5
31-May-2013Delivery - workpackage 2
31-May-2013Delivery - workpackage 4
31-May-2013Delivery - workpackage 3
14-Jun-2013Closure

RAG Status

BLUE (suspended until April)

Report by Dawn Nicholls for February 2013

Achievements this period

  • N/A project on hold until April

Issues

  • N/A

Next steps

  • N/A

 

Full details can be seen in the Project Journal

FIN080 (AP Number)

Customer Interface Improvements

 

Category: Discretionary

Milestones

 

Target dateTitle
01-Mar-2013Phase 2 - Design
24-May-2013Phase 2 - Build
28-Jun-2013Phase 2 - Integration
12-Jul-2013Phase 2 - Acceptance
19-Jul-2013Phase 2 - Go-live
26-Jul-2013Phase 2 - Deployment
12-Aug-2013Closure

RAG Status

AMBER

Report by Dawn Nicholls for February 2013

Achievements this period

  • Internal review to evaluate recommendation for software re-architecture

Issues

  • Prioritisation of tasks for phase 2 given the inability to carry-over to 13/14

Next steps

  • Agree priorities with FInance and re-plan project accordingly
  • Complete design for prioritised tasks

 

 Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

 

Category: Discretionary

Milestones

---

---

--- 

RAG Status

SUSPENDED

Report by Rhian Davies for October 2012

Project suspended

FIN083  (AP23-003)

eFinancials Upgrade

 

Category: Compliance

Milestones

 

 

  
27-Mar-2013Deployment Sign Off
10-Apr-2013Closure

 

RAG Status

GREEN

Report by Morna Findlay for Rhian Davies for February  2013

  Achievements in this period
  1. UAT  completed.

  2. Testing of interfaces to EFIN complete (  Estates Lease module not signed off)

  3. Acceptance review  approved

  4. LIVE deployment plan completed

  5. Finance  tested Serengeti on DEV and TEST

  6. LIVE upgrade completed ahead of schedule.

  7. 110 JIRA issues closed or resolved.

 

Outstanding Issues
  1. PECOS interface (awaiting information from Business owner)

  2. Estates Lease module interface (fix awaited from ABS)

  3. Salary forecasting

  4. Outstanding JIRA issues (90)

  5. POPR50 issue (fix awaited from ABS)

  6. Batch posting issue (possible solution under investigation in TEST

 

Next Steps
  1. Prioritise and resolve remaining JIRA issues 

  2. Decomissioning of old databases  and environments.

  3. Deployment of Supplier Self-Service Portal

  4. Deployment of Single-Sign-on and Launchpad

  5. Deployment sign-off review.

 

The project RAG status has been set to GREEN.

 

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

 

15-Mar-2013Project Brief signed off
29-Mar-2013Prioritised list of requirements agreed
15-May-2013System Design signed off
27-Sep-2013UAT (for final release) signed off
25-Oct-2013Deployment signed off
15-Nov-2013Closure

 

 

RAG Status:  GREEN

Report by Jill Nicoll for February  2013

Achievements in last period:
 
 
  • Project website set up.
  • Project planned in Asta, and resources requested.
  • Project Brief drafted and submitted to Programme Manager for initial review.
  • Meeting invitations issued for Analysis and Design stages.

Issues:

  • n/a

Next Steps:

  • Project Brief to be completed, reviewed by Project Sponsor, and signed off.
  • Business Analysis to be completed, reviewed by Stakeholder team, and signed off.
  • Resources to be secured.

 

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

31-Mar-13 Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for February 2013

 

Achievements in last period:

  • Project manager assigned (Louise Heathcote)

 

Issues

  • None

 

Next Steps

  • Kick off meeting with Finance
  • Complete Planning phase

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

 

Milestones

31-Mar-13 Planning

 

 

 

RAG Status:  GREEN

Report by Rhian Davies for February 2013

 

Achievements in last period:

  • Project manager assigned (Laura Bell)

 

Issues

  • None

 

Next Steps

  • Kick off meeting with Finance
  • Complete Planning phase

 

Section Four: Closed or Withdrawn Projects

 

 

 

 

 

 

Project InfoProject Managers Commentary

FIN082

HMRC Real Time Information

Compliance 

Report by Jill Nicol

This project was closed on 10-Aug-2010

Please see the Completion Report for further information.  

AP23-055

Rolling out Finance BOXI Reports

 

Funded 

Report by Rhian Davies

This project was withdrawn from the 12/13 programme.

FIN072 (AP01-008)

eTime

 

Category: Compliance

Report by Jill Nicol

This project was closed on 30-Nov-12.

Please see the Completion Report for further information.

FIN077

Control Account Balancing

 

Category: /Compliance

Report by Sue Woodger 

This project was closed 1 February 2013

Please see the Completion Report

FIN084

eStores Rollout

Category : Discretionary

 

Report by Dawn Nicholls

This project was closed on 20th December 2012