Report for February 2013
- Report Date
- February 2013
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP12-017 Decommissioning of ERA
Compliance
Planning March 2013 Delivery October 2013 RAG Status GREEN | Plan The project is scheduled to start in March 2013, following the eFinancials Upgrade.
Dependencies This project cannot start until all activity involving ERA is transferred to an alternative solution. |
AP23-059 eExpenses- Business Case
Compliance
Planning March 2013 Delivery August 2013 RAG Status GREEN | Plan The project is due to start in March 2013, following the eFinancials Upgrade.
Dependencies The project has no dependencies on other activity, however it is dependent on resource availability within Finance, so has been scheduled following the eFinancials Upgrade. |
AP23-056 International Bank Validation
Funded Planning April 2013 Delivery December 2013 RAG Status GREEN | Plan The project is due to start in April 2013.
Dependencies |
AP89-008 FPM for eInvoicing
Discretionary Planning tbc Delivery tbc RAG Status GREEN | Plan This project has been delayed to 13/14 following the Mid Year Review.
Dependencies
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing
Category: Funded Milestones --- --- --- RAG Status SUSPENDED
| Report by Rhian Davies for October 2012 Project suspended
| ||||||||||||||||
FIN076 (AP12-029) Student Finance Channel - Further Developments for Staff and Students
Category: Discretionary Milestones
RAG Status GREEN (assuming revised budget approved at WIS 08/03/13) | Report by Susan McKeown for February 2013 Achievements in Last Period
Issues
Next steps
| ||||||||||||||||
FIN078 (AP Number) eFin Journal Auto-Upload
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for February 2013 Achievements this period
Issues
Next steps
Full details can be seen in the Project Journal | ||||||||||||||||
FIN079 (AP Number) LEAN- Review of Financial Systems
Category: Discretionary Milestones
RAG Status BLUE (suspended until April) | Report by Dawn Nicholls for February 2013 Achievements this period
Issues
Next steps
Full details can be seen in the Project Journal | ||||||||||||||||
FIN080 (AP Number) Customer Interface Improvements
Category: Discretionary Milestones
RAG Status AMBER | Report by Dawn Nicholls for February 2013 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||
FIN081 (AP Number) Document Management for Finance Applications
Category: Discretionary Milestones --- --- --- RAG Status SUSPENDED | Report by Rhian Davies for October 2012 Project suspended | ||||||||||||||||
FIN083 (AP23-003) eFinancials Upgrade
Category: Compliance Milestones
RAG Status GREEN | Report by Morna Findlay for Rhian Davies for February 2013
Achievements in this period
Outstanding Issues
Next Steps
The project RAG status has been set to GREEN.
| ||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: GREEN | Report by Jill Nicoll for February 2013 Achievements in last period:
Issues:
Next Steps:
| ||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
Milestones 31-Mar-13 Planning
RAG Status: GREEN
| Report by Rhian Davies for February 2013
Achievements in last period:
Issues
Next Steps
| ||||||||||||||||
FIN087 Credit Note/Sales Invoice Interface Changes Category: Funded
Milestones 31-Mar-13 Planning
RAG Status: GREEN | Report by Rhian Davies for February 2013
Achievements in last period:
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN082 HMRC Real Time Information Compliance | Report by Jill Nicol This project was closed on 10-Aug-2010 Please see the Completion Report for further information. |
AP23-055 Rolling out Finance BOXI Reports
Funded | Report by Rhian Davies This project was withdrawn from the 12/13 programme. |
FIN072 (AP01-008) eTime
Category: Compliance | Report by Jill Nicol This project was closed on 30-Nov-12. Please see the Completion Report for further information. |
FIN077 Control Account Balancing
Category: /Compliance | Report by Sue Woodger This project was closed 1 February 2013 Please see the Completion Report |
FIN084 eStores Rollout Category : Discretionary
| Report by Dawn Nicholls This project was closed on 20th December 2012 Please see the Completion Report for further information |