Report for January 2019

Report Date
January 2019

Resource Position 

 

 

Forward Look

 

 

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

FIN126 - Making Tax Digital & Essential Financial System Compliance Updates

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Due to be initiated Feb 2019.

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN119 (AP67-024)

eInvoicing

Core Funded

Agreed at WIS 25-Jan-2019:

Target Date Title  
01-Mar-2019   Development & Deployment of the API / XML Handler  
26-Mar-2019 On-board the First 3 Suppliers  
23-Apr-2019 On-board the Second 5 Suppliers  
10-May-2019 Phase 2 – Deployment sign off  
17-May-2019 Project closure  

 

RAG Status : GREEN

 

Report By Richard Bailey for January 2019

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • Work continuing against work packages / development of the API / XML Handler
  • PICCL created and milestones / budget has been readdressed inline with resource bookings / availability

 

Issues

  • None

 

Next Steps

  • Continue work packages / development of the API / XML Handler
  • Agree a new 'LIVE' SR with the SG

 

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Closure Review 31-Jul-2019

 

RAG Status: GREEN

 

 

 

Report By Tim Gray for January 2019

 

Achievements in Last Period

  • 10 days added to the project, for further media production
  • Closure milestone moved out to the end of July to allow regular media production
  • No production activity this month, awaiting confirmation from Finance on their media schedule.

Issues

  • None

Next Steps

  • Confirm and plan future content production.

 

 

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date
Planning 01-Feb-2019
Analysis 03-May-2019
Solution Options 07-Jun-2019
Implementation Plan 28-Jun-2019
Delivery 30-Sep-2019
Closure 28-Oct-2019

 RAG Status : GREEN

 

Report by Ben Armstrong for January 2019

Achievements

  • Review and update of project brief
  • Stakeholder meeting held to finalise project brief
  • Call booked with eFinancials system supplier to review GDPR patch

Issues

  • None noted

Next Steps

  • Confirm quality of GDPR patch for eFinancials with Finance and supplier

  • Kick off analysis of data across Finance systems for GDPR compliance

 

FIN128

FPM Upgrade

Core Funded

Milestones

Milestone Due Date
Planning 01-03-2019
Delivery 26-04-2019
Closure 10-05-2019

 

 RAG Status : GREEN

Report by Leon Toland for January 2019

Achievements in Last Period:

  • The project request forms (ASTA and In-Year) for project FIN128 were reviewed and approved by WIS on January 25th,  2019.
  • The project has now moved into the Planning stage.
  • The initial draft of the Project Brief has started development.

Issues:

  • None to report

Next Steps:

  • Further development and review of the Project Brief
  • Advanced (FPM supplier) to provide final confirmation of release date for FPM v2.4.0.16 (target release package for FIN128)

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

 

Closure Report

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Closure Report