Report for December 2018

Report Date
December 2018

Resource Position 

 

Forward Look

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

FIN126 - Essential Finance System Compliance Updates and Document Revitalisation

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Expected to commence in early 2019.

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN118 (AP56-016)

eFinancials upgrade

Funding: TBC

 

Target Date

Title

Completed

Readiness / Approval to Go-Live

Completed

Go-Live

11-Jan-2019

Deployment Sign-off

25-Jan-2019

Project Closure

 

RAG Status : GREEN

 

 

 

 

 

 

Report By Lee-Ann Simpson for December 2018

Achievements in Last Period

  • eFinancials monitored for stability across December;
  • Lessons Learned session held with final version out for review with the key stakeholders.

Issues 

  • Various FPM issues experienced in the weeks following Go-Live which continued into December and resulted in additional support time being spent on the project.
  • Project Manager/ Apps Man and Dev Tech spending significantly more time post Go-Live than anticipated due to the errors being identified by the business.  Most errors were resolved in a timely fashion by the project team.

Next Steps 

  • DSOR to be signed off (meeting scheduled for 11th January);
  • Final version of the Lessons learned to be circulated (to be returned by the project team on 16th January) ;
  • Decommissioning to be undertaken (Initial discussion - 9th January 20019);

FIN119 (AP67-024)

eInvoicing

Core Funded

Agreed at WIS 12-Oct-2018, as stated in this report these will need to be reviewed again in the very near future:

Target Date Title  
08-Nov-2018 Development & Deployment of the API / XML Handler  
22-Feb-2019 On-board the First 3 Suppliers  
22-Mar-2019 On-board the Second 5 Suppliers  
29-Mar-2019 Phase 2 – Deployment sign off  
12-Apr-2019 Project closure  

 

RAG Status : AMBER

 

Report By Richard Bailey for December 2018

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • Work continuing against work packages / development of the API / XML Handler

Issues

  • None

Next Steps

  • The Milestones need to be re-reviewed / realigned to address time lost to other Highest Priority Projects during November (notably FIN118 eFinancials Upgrade and Migration and MLE004 Lecture Room Recordings).  It is not expected that delivery / closure milestones are greatly affected
  • Submit a PICCL to WIS to realign the Project milestones once works / test scheduled are firmed up again
  • Continue work packages / development of the API / XML Handler

 

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Core Funded

  Title  
Completed Acceptance Testing v4.1 (ASOR)  
 Completed Deploy/Deliver v4.1 (Major)    
Completed IS Integration v5 Complete  
Completed Acceptance Testing v5 (ASOR)  
Completed Deploy/Deliver v5 (Major)  
25-Jan-2019 Project Closure (Major)  
25-Jan-2019 DSOR (plus deployment checklist)

 

RAG Status : Amber

 

 

 

 

 

 

 

Report By Lee-Ann Simpson for December 2018

Achievements

  • Final changes deployed to LIVE v5;
  • User Acceptance Testing to be undertaken in v5 completed and signed off;
  • Closure report created and shared with stakeholders for sign off.

Issues 

  • No issues as delay due to FIN118 deployment.

Next Steps 

  • Project to be closed.
  • Remaining work which was unable to be completed within FIN123 to be carried forward to the next revitalisation project (FIN126).

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Closure Review 28-Feb-2019

 

RAG Status: GREEN

 

 

 

Report By Tim Gray for December 2018

Achievements in Last Period

Issues

  • None

Next Steps

  • Finance has requested that the project remain open so that 4 unused days can be utilised for creating more content. Some more days may be added to the project.
  • Agree on the next content with Finance

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date
Planning 30-Nov-2018
Delivery 24-May-2019
Closure 21-Jun-2019

 

 RAG Status : AMBER

Report by Ben Armstrong for December 2018

Achievements

  • DPIA completed in DPIA workshop with Finance team and Data Protection Officer
  • Drafted project brief and high level plan
  • Viewed demo of suppliers' GDPR patch for eFinancials

Issues

  • No agreement yet on project estimate - to be agreed with sponsor and team - cost RAG marked as AMBER
  • GDPR patch for eFinancials not fit for purpose, as it stands - feedback has been provided with supplier and awaiting confirmation - scope RAG marked as AMBER
  • Further time required to complete Planning due to reflection time on DPIA to feed into the project brief and plan - to be incorporated - time RAG marked as AMBER

Next Steps

  • Confirm quality of GDPR patch for eFinancials with Finance and supplier

  • Sign off project brief, plan and estimate to confirm and sign off end of planning stage

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

 

 