Report for November 2018
- Report Date
- November 2018
Resource Position
Forward Look
Section 2: Projects Not Started
Project Info |
Programme Managers Commentary |
FIN126 - Essential Finance System Compliance Updates and Document RevitalisationPlanning - tbc Delivery - tbc RAG Status : GREEN |
Expected to commence in early 2019. |
Section 3: Projects in Progress
Project Info |
Project Managers Commentary
|
|||||||||||||||||||||||
FIN118 (AP56-016)eFinancials upgrade Funding: TBC
RAG Status : GREEN
|
Report By Lee-Ann Simpson for November 2018 Achievements in Last Period
Issues
Next Steps
|
|||||||||||||||||||||||
FIN119 (AP67-024)eInvoicing Core Funded Agreed at WIS 12-Oct-2018, as stated in this report these will need to be reviewed again in the very near future:
RAG Status : AMBER
|
For reference: SG = Scottish Government, SGS = Scottish Government Solution Achievements this Period
Issues
Next Steps
|
|||||||||||||||||||||||
FIN123 (AP56-016)Annual Finance Document Revitalisation 17/18 Core Funded
RAG Status : AMBER: Having been red in September, FIN123 has been unable to complete deliverables due to consultant availability to undertake all required work. This impacted the milestones and has resulted in a number of risks and issues to the project which effects stakeholders in Finance (Risk 7(Change to Project Scope) , 8 (Delay to Documentation being Updated), 9(Unable to complete all required changes within allocated time), and Issue 6 (Delay to Milestones)). The Project Team has however now agreed a reduction in scope (moving outstanding compliance requirements from this 2017/18 project into 2018/19 annual project) and a route to closure for this project. This will be undertaken to ensure alignment with dependant project, FIN118. FIN123 will remain as AMBER for November due to the delay in completing the project as a result of the FIN118 deployment and subsequent work undertaken to stabilise the FPM application. As a result, there was no available resource to progress with the outstanding actions to allow FIN123 to be completed. Above milestone dates will change once these have been approved via WIS on 07/12/2018.
|
Report By Lee-Ann Simpson for November 2018 AchievementsDue to FIN118 deploying mid November, no additional work was undertaken on FIN123 as the remaining work required was dependant on FIN118 being successfully deployed. Issues
No issues as delay due to FIN118 deployment. Next Steps
|
|||||||||||||||||||||||
FIN125Media Production for Annual Report and Accounts Sponsor Funded Milestones
RAG Status: GREEN
|
Report By Tim Gray for November 2018 Achievements in Last Period
Issues
Next Steps
|
|||||||||||||||||||||||
FIN127Finance General Data Protection Regulation (GDPR) Core Funded Milestones
RAG Status : AMBER |
Report by Ben Armstrong for November 2018 Achievements
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|
Attachment | Size |
---|---|
![]() | 61.73 KB |