Report for October 2018

Report Date
October 2018

Resource Position 

 

Forward Look

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

FIN126 - Essential Finance System Compliance Updates and Document Revitalisation

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Expected to commence in early 2019.

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN118 (AP56-016)

eFinancials upgrade

Funding: TBC

 

Target Date

Title

26-Oct-2018

Readiness / Approval to Go-Live

12-Nov-2018

Go-Live

30-Nov-2018

Deployment Sign-off

14-Dec-2018

Project Closure

 

RAG Status : GREEN

 

 

 

 

 

 

Report By Lee-Ann Simpson for October 2018

Achievements in Last Period

  • Repeat PEN Testing completed with final report sent around the project team and CISO for review;
  • DR Testing completed;
  • All ‘showstopper’ JIRAs reviewed and actioned accordingly;
  • eExpenses and FPM signed off by Finance;
  • Change Freeze in place for eFinancials LIVE version.

Issues 

  • eExpenses will be in a shared instance rather than an isolated instance due to the timescales remaining before deployment.
  • ‘Readiness/Approval to Go-Live’ to be signed off by the project team.
  • Resource conflict received/required across October which impacted upon the overall budget.

Next Steps 

  • UAT to be signed off formally;
  • Go/No Go Meeting;
  • Deployment of the eFinancials upgrade

Revised milestones across the closure of FIN118:

Target Date

Previous Date

Title

26-Oct-2018

03-Apr-2018

Readiness / Approval to Go-Live

12-Nov-2018

16-Apr-2018

Go-Live

30-Nov-2018

11-May-2018

Deployment Sign-off

14-Dec-2018

08-Jun-2018

Project Closure

  •  

FIN119 (AP67-024)

eInvoicing

Core Funded

Milestones agreed at WIS 21-Sep-2018, as stated in this report these will need to be reviewed again in the very near future:

Target Date Title  
21-Sep-2018            Complete Analysis (Process Mapping / Applications and SDS Document / Suppliers Identified)    
28-Sep-2018  Phase 2 – Create work packages / discrete backlog items  
19-Oct-2018 Development & Deployment of the API / XML Handler  
22-Feb-2019 On-board the First 3 Suppliers  
22-Mar-2019 On-board the Second 5 Suppliers  
29-Mar-2019 Phase 2 – Deployment sign off  
12-Apr-2019 Project closure  

 

RAG Status : AMBER

 

Report By Richard Bailey for October 2018

Report for October 2018

Report Date
October 2018

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • Work had started on the work packages / development, however software development resource has been lost, please see Issues blow
  • Successfully connected to / engaged with the SG TEST environment
  • Test data was identified
  • Work started to develop the API / XML Handler
  • Project priority was agreed at WIS to be increased to highest

Issues

  • All of the following risks have been impacted (all AMBER) because Software Development Resource has been lost in the near future to two other highest priority Projects, to ensure their smooth delivery - FIN118 eFinancials Upgrade and Migration and MLE004 Lecture Room Recordings.  FIN118 is due to go LIVE over the weekend of 09-12th November 2018.  The Project Manager has worked closely with the Resourcing Manager to see that Resource bookings are kepts as close to the original bookings.  Once FIN118 has gone live a meeting will be held with the Business Project Team to ensure timings are still managable and a PICCL will be raised to reset the milestones.  At this stage and providing FIN118 is deployed with no further issues it is believed that milestones will move out by approximately 2 to 3 weeks, based on provisional resource bookings secured.    This does still need ratification with the Finance Team that will be conducting testing:

Next Steps

  • Review the Resourcing situation closely, paying close attention to FIN118 and its deployment
  • Submit a PICCL to WIS to realign the Project milestones once Resource is re-secured / firmed up again
  • Continue work packages / development of the API / XML Handler

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Core Funded

  Title  
10-Aug-2018  Acceptance Testing v4.1 (ASOR)  
 13-Aug-2018 Deploy/Deliver v4.1 (Major)    
13-Aug-2018 IS Integration v5 Complete  
17-Aug-2018 Acceptance Testing v5 (ASOR)  
20-Aug-2018 Deploy/Deliver v5 (Major)  
31-Aug-2018 Project Closure (Major)  
31-Aug-2018 DSOR (plus deployment checklist)

 

RAG Status : Amber

 

 

 

 

 

 

 

Report By Lee-Ann Simpson for October 2018

Achievements

  • 2 x overall file’s promoted to live.
  • Consultant provided updated file to address issues identified in LIVE with repeat UAT completed (v4.1);
  • UAT underway for v5 (copy of LIVE file)

Issues 

  • Unable to progress to v5 earlier that the end of October due to the updated file not being received until 26th October at which point repeat UAT on the current version was required to be completed

Next Steps 

  • Approval from WIS of change to scope/milestones due to delay received from contractor;
  • User Acceptance Testing to be undertaken in v5 once completed;
  • All remaining changes to implement into Live once acceptance has been completed and signed off.
  • Once v4.1 has been completed and is working correctly, all changes need to be applied v5 Test environment before repeating the acceptance testing prior to deployment into Live.
  • Closure report to be completed;
  • Project to be closed.

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Filming complete 09-Nov-2018
  Post-production complete 30-Nov-2018
  Deliver Media 03-Dec-2018
  Closure Review 21-Dec-2018

 

RAG Status: GREEN

 

 

 

Report By Tim Gray for October 2018

Achievements in Last Period

  • Planning completed
  • Scripts finalised
  • Film locations secured
  • Student assistant appointed

Issues

  • None

Next Steps

  • Filming on 5th November
  • B-roll (additional footage) to be filmed on 6th November
  • Post-production

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date
Planning 30-Nov-2018
Delivery 24-May-2019
Closure 21-Jun-2019

 

 RAG Status : AMBER

Report by Ben Armstrong for October 2018

Achievements

  • Held kick-off meeting to discuss project scoping, including Data Protection Officer
  • Further meeting with Finance to confirm project planning actions

Issues

  • No Finance action plan in place to address GDPR implementation; to address this the team will complete Data Protection Impact Assessments (DPIAs) to establish the requirements and from there, draw up an action plan.  As this is different to the expected scope from the Annual Planning document, the project has been marked as Amber for now. 

Next Steps

  • Undertake DPIAs

  • View demo of suppliers' GDPR patch for eFinancials

  • Discussion with supplier about data purging functionality in eFinancials

  • Agree scope for project to confirm and sign off end of planning stage

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

 

 