Report for September 2018

Report Date
September 2018

Resource Position 

 

Forward Look

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

FIN126 - Essential Finance System Compliance Updates and Document Revitalisation

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Expected to commence in early 2019.

FIN127 - Finance General Data Protection Regulation (GDPR)

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

This work is expected to be initiated in October 2018.  A Project manager has yet to be identified.

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN118 (AP56-016)

eFinancials upgrade

Funding: TBC

 

Target Date

Title

26-Oct-2018

Readiness / Approval to Go-Live

12-Nov-2018

Go-Live

30-Nov-2018

Deployment Sign-off

14-Dec-2018

Project Closure

 

RAG Status : GREEN

 

 

 

 

 

 

Report By Lee-Ann Simpson for September 2018

Achievements

  • UAT at 90+% by end of September (including subsidiary systems and eExpenses)
  • eExpenses upgrade completed.
  • PEN Testing updates received from Supplier to be applied to DEV.

Issues 

  • DR Testing still to be scheduled.
  • Issues confirming eExpenses resources resulted in a resource conflict having to be raised.

Next Steps 

  • Complete 2nd round of PEN Testing once issues have all been resolved.
  • Confirm and then action the DR Test plan.
  • Continue with all outstanding tasks to allow for ‘Readiness/Approval to Go-Live’ Milestone to be achieved (Scheduled: 26th October 2018).

FIN119 (AP67-024)

eInvoicing

Core Funded

Milestones agreed at WIS 21-Sep-2018:

Target Date Title  
21-Sep-2018            Complete Analysis (Process Mapping / Applications and SDS Document / Suppliers Identified)    
28-Sep-2018  Phase 2 – Create work packages / discrete backlog items  
19-Oct-2018 Development & Deployment of the API / XML Handler  
22-Feb-2019 On-board the First 3 Suppliers  
22-Mar-2019 On-board the Second 5 Suppliers  
29-Mar-2019 Phase 2 – Deployment sign off  
12-Apr-2019 Project closure  

 

RAG Status : GREEN

Report By Richard Bailey for September 2018

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements

  • Resource aligned with the SG, the SG now have a TEST environment up and running that can be utilised by the UoE Development Team
  • Senior Analyst Developer has completed the SDS, which was reviewed by the Project Team / Stakeholders at a meeting 18-Sep-2018 
  • Project work packages have been planned and User Stories added into JIRA
  • PICCL submitted to WIS and approved to reset milestones

Issues

  • None

Next Steps

  • Start work packages / development
  • Connect to / engage with the SG TEST environment
  • Identify and utilise Test data
  • Develop the API / XML Handler
  • Submit a PICCL to WIS to look to increase overall project priority

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Core Funded

  Title  
10-Aug-2018  Acceptance Testing v4.1 (ASOR)  
 13-Aug-2018 Deploy/Deliver v4.1 (Major)    
13-Aug-2018 IS Integration v5 Complete  
17-Aug-2018 Acceptance Testing v5 (ASOR)  
20-Aug-2018 Deploy/Deliver v5 (Major)  
31-Aug-2018 Project Closure (Major)  
31-Aug-2018 DSOR (plus deployment checklist)

 

RAG Status : RED

 

 

 

 

 

 

 

Report By Lee-Ann Simpson for September 2018

Achievements

  • 1 x file promoted to live.
  • Consultant booked back in to complete the remaining requirements into Test;
  • User Acceptance Testing undertaken in v4.1 completed;

Issues 

Unable to complete deliverables due to consultant availability to undertake all required work. This impacted the milestones and has resulted in a number of risks and issues to the project which effects stakeholders in Finance (Risk 7(Change to Project Scope) , 8 (Delay to Documentation being Updated), 9(Unable to complete all required changes within allocated time), and Issue 4 (Delay to Milestones)). The Project Team is looking to progress a reduction in scope (moving outstanding compliance requirements from this 2017/18 project into 2018/19 annual project). This will be undertaken to ensure alignment with dependant project, FIN118.

  • Issues identified in LIVE after the file had been promoted to LIVE.  Issues referred back to contractor for review.
  • Additional files not promoted to LIVE due to incomplete UAT.

Next Steps 

  • Approval from WIS of change to scope;
  • User Acceptance Testing to be undertaken in v5 once completed;
  • All remaining changes to implement into Live once acceptance has been completed and signed off.
  • Once v4.1 has been completed and is working correctly, all changes need to be applied v5 Test environment before repeating the acceptance testing prior to deployment into Live.
  • Closure report to be completed;
  • Project to be closed.

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Planning Review 05-Oct-2018
  Pre-production complete 31-Oct-2018
  Filming complete 09-Nov-2018
  Post-production complete 30-Nov-2018
  Deliver Media 03-Dec-2018
  Closure Review 21-Dec-2018

 

RAG Status: GREEN

 

 

 

Report By Tim Gray for September 2018

Achievements 

  • Some work progressed on planning
  • Dates for filming agreed

Issues

  • None

Next Steps

  • Complete planning
  • Book filming locations
  • Finalise scripts

 