Report for April 2018

Report Date
April 2018

Resource Position 

Forward Look

 

Section 2: Projects Not Started

Project Info Programme Managers Commentary

FIN121

eTime 17/18 (eSignature)

Planning - tbc

Delivery - tbc

 RAG Status : Amber

 Update requested on project withdrawal from Finance.

 

 

Section 3: Projects in Progress

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

Core funded

Target Date

Title

03-Apr-2018

Readiness / Approval to Go-Live

16-Apr-2018

Go-Live

11-May-2018

Deployment Sign-off

08-Jun-2018

Project Closure

 

RAG Status: RED

 

Report by Chris Orrell

Achievements in Last Period

  • A strategic options paper detailing the various upgrade options that in theory may be available has been prepared and reviewed by the University. At the time of preparing this report option 1 appears likely to be the recommended option though additional detail and senior management review is required. This option paper included costs to date, costs directly attributable to the issue and estimated costs to complete for the supplier recommended approach.
  • DEV has been upgraded to Oracle 12.1 eFinv5 using Data Guard and as expected no issues have been encountered and this confirms with the supplier that this method of data export / import can be performed with eFinancial upgrades.
  • A revised draft plan for November go-live with Oracle 12.1 has been prepared but this needs to be reviewed in light of agreed update dates for TEST and Pre-LIVE of 9th and 24th May respectively.
  • Security Pen Testing completed for eFin except for Supplier Self Service (SSS) and an interim report has been issued. Security Pen Test Supplier will complete the pen testing of SSS once a defect has been fixed.
  • All JIRAs have been reviewed to identify those which should be resolved now rather than waiting for a repeat of UAT.
  • Resources have been booked to complete eExpenses JIRAs and repeat UAT.
  • Finance (FIS) have agreed that if eFin upgrade takes place in November 2018 the upgrades to FPM and eExpenses can wait until then.

Issues

  • There is currently only one option available to the University to progress the upgrade of eFinancials this calendar year. This would mean TEST & Pre-LIVE being rebuilt to Oracle 12.1, interface testing being repeated for DEV & TEST and Finance repeating all of UAT. Earliest go-live is indicated at November 2018. However, the University must decide upon the favoured option and agree a route forward with the supplier.
    • All project milestones currently void until the project has been re-planned.
  • Asta requires a complete update to reflect whatever proves to be the agreed approach.
    • The estimate to complete should be complete within this report should be completely ignored as it will be approximately 318 IS days.

Next Steps

  • Finalise a project plan for the agreed approach to resolve the sequencing / Oracle 12.1 issue, then book resources against this, update projects web site and submit new milestones to WIS.
  • All JIRAs not to be fixed now to be closed.
  • Fix the SSS defect and complete security pen testing.

RAG Commentary

Issue: The project cannot go-live with Oracle 12.2 and so must be re-planned. An options paper has been prepared and reviewed and the approach to be taken by the University needs to be agreed both internally and with the supplier. This has been escalated to IS senior management.

FIN119 (AP67-024)

eInvoicing

 

Target Date Title
22-Jun-2018   Complete Analysis (Process Mapping / Applications and Data Architecture (ADA) Document / Suppliers Identified)
29-Jun-2018 Phase 2 – Create work packages / discrete backlog items
05-Oct-2018 Development & Deployment of the API / XML Handler
12-Oct-2018 On-board the First 3 Suppliers
19-Oct-2018 On-board the Second 5 Suppliers
24-Oct-2017 Phase 2 – Deployment sign off
02-Nov-2018 Project closure

 

RAG Status : AMBER

 

Report by Richard Bailey

Report Date
April 2018

Achievements this Period

  • Software Development Resource is booked against the project (see the Issues section below)   
  • A PICCL was submitted to WIS 27/04/2018 to reset the milestones / extend the project into the 2018/19 financial year.
  • Progress has been made with the Applications and Data Architecture (ADA) Document.
  • The Senior Analyst Developer has been secured to plan subsequent WPs (based on the decisions made / the Project Proposal & ADA Documents) in May.

Issues

  • RISK:  Securing Software Development Resource - Amber.   PM has worked closely with the Resourcing Manager (Software Development).  It was apparent that it would not be possible to secure Software Development Resource to complete all of the tasks required in the 17-18 financial year.  Therefore Resource has been booked / secured to complete the required works at the first available opportunity, which runs the project into the 18-19 financial year.
  • RISK:  Securing Budget In 2018/19 Financial Year - Amber.  At this stage the budgets for 2018/19 are yet to be secured / agreed and there is a risk that the budget to secure the remainder of the works will not be made available in the 2018/19 year.

Next Steps

  • Submit a PICCL to WIS 04/05/2018 to raise the Project Priority from Normal to Higher in order to protect resource bookings / working alongside SG Team.
  • Plan the subsequent WPs (based on the decisions made / the Project Proposal & ADA Documents) with the Senior Analyst Developer.
  • Complete the Applications and Data Architecture (ADA) Document and achieve sign off.
  • Get the SR document agreed and sign off / engage with the SG
 

RAG Commentary

Change: The change to the project timescales and moving a proportion of the development to the 2018-19 Financial Year creates a risk around securing budget to complete the tasks required in that year as budgets for 2018-19 are not yet agreed / set.

 

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Planning - tbc

Delivery - tbc

Core funded

 

RAG Status : GREEN

Report by Lee-Ann Simpson

Report Date
April 2018

Achievements

  • Kick off meeting with Finance undertaken to obtain commitment of Finance resource;
  • Reached out to additional key finance stakeholders, setting up initial meeting in order to identify the documents which will be in scope for this project (meeting scheduled for 01/05/2018).
  • Discussed project with Service Excellence whom advised they do not need to be sighted in this project currently as it does not impact upon the Core System Procurement.  This will be reviewed throughout the duration of the project. 

Issues 

  • There is a current potential issue regarding IS Service Development resource.  This is being reviewed and discussed as part of the planning stage.

Next Steps 

  • Complete planning for the project.
  • Project brief to be signed off.
  • System Design to be commenced.

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN116 (AP67-022)

eTime - guaranteed hours

Category: Discretionary

Project Manager - Richard Bailey

Project closed 15th September 2017

Completion Report

FIN117 (AP56-054)

Finance BI Improvement

Category: Discretionary

 

Project Manager - Richard Bailey

Project closed 4th August 2017

Completion Report

FIN108 (AP56-042)

Essential enhancements (FIS)

Category: Discretionary

Project Manager - Emma McNab

Project Closed 6th October 2017

Completion Report

FIN 120 (AP67-025)

Fraud protection for Accounts Payable

Category: Discretionary

Project Manager - Emma McNab

Project Closed 12th January 2018 

Completion Report

FIN122

Decommissioning ABS Expense System 

Project Manager - Emma McNab

Project Withdrawn 2nd February 2018 

 

AttachmentSize
Image icon finapril2.png58.89 KB
Image icon finapril.png81.38 KB