Report for October 2017

Report Date
October 2017

 

Resource Position 

Forward Look

Section 2: Projects Not Started

Project Info Programme Managers Commentary

AP67-022

eTime 17/18 (eSignature)

Planning - tbc

Delivery - tbc

 RAG Status : Amber

Awaiting confirmation from Finance if this project is to progress.  Issue escalated to Portfolio Manager

AP78-012

Decommissioning ABS Expense System 

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Discussion had with Finance and Application Management regarding dependencies with Fin118.  Progress TBC

 

 

Section 3: Projects in Progress

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

Core funded

Target Date

Title

09-Jun-2017

End of Analysis / Design

01-Dec-2017

End of DEV / sign-off

27-Feb-2018

Readiness / Approval to Go-Live

12-Mar-2018

Go-Live

30-Apr-2018

Deployment Sign-off

31-May-2018

Project Closure

 

RAG Status: Amber

Report by Chris Orrell for October 2017

Achievements in Last Period

  • Issues with Bank Wizard and Document Imaging in TEST have been fixed.
  • Issues in TEST relating to sequencing have been fixed.
  • Interface testing is continuing and additional resource has been secure to help with fixing JIRAs. Currently 46% passed, 15% blocked (5 from 6 which can't be tested in DEV), 5 require retest, 6 failed, 4 untested.

Issues

  • UAT was stopped due to issues with sequencing however a fix was supplied which works.
  • Issues with in-house applications set up for DEV , many relating to the migration to Oracle 12c database. This is delaying completing DEV and then setting up these applications in TEST.
  • Impact on overall timing from later TEST installation date, issues stopping UAT.
  • System performance is slower than v4.1 and this remains an issue yet to be investigated.
  • Project budget forecasts an increase from 575 to 686 days. PICCL to be raised.
  • Cold fusion application expenses may not be supported by Oracle 12c. Mitigation may be moved to Coldfusion 11, decision regarding approach required.

Next Steps

  • Confirm additional resource to support DEV work. Complete interface testing of in-house applications.
  • Set up in-house applications on TEST, complete interface testing and pass to Finance for UAT.
  • Prepare budget report and PICCL.
  • Prepare revised project plan.
  • Complete change control procedure.
  • Schedule security pen testing.
  • Defining and communicating change Control Board terms of reference.

RAG Commentary

ISSUE: Using later TEST upgrade installation dates of 25th September (back from 4th), issues encountered in TEST and delay to in-house application set up in DEV will impact project timing. Budget report and PICCL required. No SMT action required.

FIN119 (AP67-024)

eInvoicing for Medium Suppliers

 

Target Datesort descending Title
10-Nov-2017 End of Planning
17-Nov-2017 Phase 1 – Engage with the Scottish Government Team
15-Dec-2017 Phase 1 - Analysis completed – in house / CIBR solutions
15-Dec-2017 Phase 1 - Analysis completed – Scottish Government solution
22-Dec-2017 Phase 1 – Decision made on solution(s) to implement
22-Dec-2017 Phase 1 – Suppliers identified / agreed
19-Jan-2018 Phase 2 – Create work packages / discrete backlog items
09-Feb-2018 Phase 2 – Deploy any technology required to implement the Scottish Solution
28-Feb-2018 Phase 2 – Time and budget allowing add the Suppliers to the solution(s)
16-Mar-2018 Phase 2 – Deployment sign off
30-Mar-2018 Project closure

 

 

RAG Status : GREEN

Report by Richard Bailey for October 2017

Achievements this Period

  • High level scope and milestones agreed and a Project Brief was passed by WIS 27/10/2017
  • Project Team agreed
  • Initial contact made with Scottish Government (SG) Team
  • BA investigating  the current in house solutions / gaps in knowledge in order to land a Supplier on the current UoE eInvoicing solutions

 

Next Steps

  • Understand exactly what is required from a technical / skill set point of view to understand if we are able to implement the SG Solution, an initial meeting is scheduled Friday 10/11/2017 with the SG Team
  • Hold a follow up meeting, assuming the SG Solution is achievable, with the SG and Project Teams, notably including the Business representatives, to ensure the SG Solution meets Finance / Procurement's requirements
  • Produce an estimate of effort / duration to add a Supplier to the CIBER / inhouse eInvoicing solutions
  • The Serengeti system will need careful analysis / consideration to make sure it has the scalability / capacity to store the electronic invoices
  • Plan subsequent work packages

Issues

None

FIN 120 (AP67-025)

Fraud protection for Accounts Payable

Target Date

Title

07-Nov-2017

Readiness / Approval to Go-Live

09-Nov-2017

Go-Live

16-Nov-2017

Deployment Sign-off

23-Nov-2017

Project Closure

 RAG Status : GREEN

 

Report by Emma McNab for October 2017

Achievements this Period

  • Brief approved
  • Jira FIN120-02 - Run various SQL scripts in eFin Test - complete
  • Jira FIN120-03 - Run various SQL scripts in eFin Live - initiated
  • Jira FIN120-04  - eExpenses Primary Affiliation Sub-Ledger Allocation Change - initiated

Next Steps

  • Complete Jira FIN120-03 and Jira FIN120-04 
  • Go Live
  • Completion report

Issues

RISK: remains in relation to alignment with FIN118 however there is currently no open issues.

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN116 (AP67-022)

eTime - guaranteed hours

Category: Discretionary

Project Manager - Richard Bailey

Project closed 15th September 2017

Completion Report

FIN117 (AP56-054)

Finance BI Improvement

Category: Discretionary

 

Project Manager - Richard Bailey

Project closed 4th August 2017

Completion Report

FIN108 (AP56-042)

Essential enhancements (FIS)

Category: Discretionary

Project Manager - Emma McNab

Project Closed 6th October 2017

Completion Report