Report for June 2017
- Report Date
- June 2017
A Programme Meeting was held on Monday 26th June. Reductions in budget were discussed and projects due to close prior to year end confirmed.
Reductions in projects FIN119 and FIN120 have been proposed due to later than expected start. A PICCL is due to go to WIS providing an overview of the current programme.
FIN115 was closed this month and FIN111 has completed maintenance and is due to close at the start of July.
Resource Position
Forward Look
Section 2: Projects Not Started
N/a
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||||
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary Milestones 24 /06/17 - Supplier On site 28/07/17 - Project Close RAG Status : Amber: Issue |
Report by Emma McNab for June 2017 Achievements this PeriodProject is awaiting approval from WIS to un suspend. All project requirements were previously successfully delivered, except for the migration of Bank Wizard for FPM. This migration had been suspended since November 2016, as the Supplier of FPM had been unable to provide a working patch for the 2 remaining issues in FPM v2.3. The Programme Manager and Business Lead agreed to suspend the project, until the Supplier has delivered a working patch for the 2 remaining FPM v2.3 issues (JIRA FIN108-66). The supplier has now confirmed that the dates of 22nd and 23rd June are available to have both a developer and consultant on site. It is now proposed FPM v2.3.0.4 is installed on Dev and Test to replace v2.3.0.2. JIRA FIN108-69 and FIN108-68. Development Technology and Application Services have both agreed to these dates and resource has been scheduled. The above dates will move the patch through dev and test however we are awaiting confirmation when it will be moved to LIVE. A further PICCL will be produced when confirmation is received and all milestones can be defined. Next Steps
IssuesAmber - Still waiting confirmation when supplier will be available to support patch move to LIVE. This may impede closure this year. Milestones to be re-planned
|
||||||||||||||||||||||||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : Amber:Issue Milestones
|
Report by Emma McNab for June 2017 Achievements this Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
FIN116 (AP67-022) eTime - guaranteed hours Category: Compliance Milestones
RAG Status : AMBER |
Report by Richard Bailey for June 2017 Achievements in last period
Issues / Risks
Next Steps
|
||||||||||||||||||||||||||||||||||||
FIN117 (AP56-054) Finance BI Improvement Category: Discretionary Milestones
RAG Status: Green |
Report by Richard Bailey for June 2017 Achievements this period
Risks
Next steps
|
||||||||||||||||||||||||||||||||||||
FIN118 (AP56-016) eFinancials upgrade Core funded
RAG Status: Green |
Report by Chris Orrell for June 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
FIN119 (AP67-024) eInvoicing for medium suppliers
RAG Status : Amber: issue |
Report by Emma McNab for June 2017 Achievements this Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
FIN 120 (AP67-025) Fraud protection for Accounts Payable
RAG Status : Amber:issue |
Report by Emma McNab for June 2017 Achievements this Period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP67-023 eCash Core funded
|
Project withdrawn |
FIN112 (AP56-921) Finance strategic review Category : discretionary / funded |
Project Manager - Dawn Holmes Project closed 2nd August 2016 |
AP45-020 Estates & Buildings - Finance interface requirements Category: Discretionary |
Project withdrawn |
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary |
Project Manager - Nikki Hackett Reed Project closed 2nd September 2016 |
FIN115 (AP67-026) Financial systems user de-provisioning Category: Compliance
|
Project Manager - Richard Bailey Project closed 16th June 2017 |
Attachment | Size |
---|---|
![]() | 38.31 KB |
![]() | 51.14 KB |
![]() | 48.14 KB |